INSTALLATION OF 440' NEW SIDEWALK SHED AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION
Patching of deteriorated concrete
INSTALLATION OF CHAIN LINK CONSTRUCTION FENCE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ALL WORK TO COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE.
Suspended scaffold in order to perform exterior facade repairs. Facade inspections to be performed. No change in use, occupancy or egress under this application.
MODIFICATION OF THE EXISTING SPRINKLER SYSTEM. ADDITION OF THE SPRINKLER HEADS.
INSTALLATION OF 570KW COGEN SYSTEM INCLUDING ALL PIPING, DUCT WORK, AND FANS. INSTALLATION OF HEAT RECOVERY SYSTEM STEAM GENERATOR INCLUDING ALL PIPING AND ASSOCIATED EQUIPMENT. PLUMBING WORK FILED SEPARATELY. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
INSTALLATION OF NATURAL GAS PIPING, REGULATOR AND METER AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Propose to create an opening and install a metal door as per the plans submitted herewith.
Propose to address ECB #35656450R, remove a window and install a metal door in its place at exposure #2 as per plans submitted herewith.
Dish Network - Installation of new cabinet on new wall mount on roof. Installation of new antenna sectors with RRH units and GPS on roof. Related service connection. All work in compliance with TPPN 5/98. No change to occupancy, use, or egress.
Decommission of existing Sprint site. Remove antennas and equipment from the roof. Service connection in basement. Initial installation approved under application #401244845
Install NEW DEP antenna site. Install (2) antennas on bulkhead facade. Install (1) DCU cabinet on roof at bulkhead facade and (1) related solar panel on bulkhead facade. No change in use, egress or occupancy.
MECHANICAL WORK TO BE FILED AT THE CELLAR LEVEL, IN CHILLER AND MECHANICAL ROOM. BUILDING 6700. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Carrier: T-Mobile. Modification of an existing antenna site. Install (9) RRUs on the roof. (3 RRUs per sector) All work is in conformance with TPPN #5/98. No change in use, egress or occupancy.