28 total · Page 1 of 2
Mechanical work associated with installing VRF refrigerant lines and indoor units from the cellar to the 29th floor in the corridors and home offices and connecting to condenser units on the roof bulkhead. No change in occupancy use or egress.
Material Hoisting Via Outrigger Beam
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER # 33 OF THE NYC CODE 2022, NO CHANGES IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED LIVE LOAD 300 AND 600 PSF SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE. SIDEWALK SHED ALONG JOHN STREET IS APPROVED FOR EQUIPMENT STORAGE. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Installation of suspended scaffold for facade inspection/repair.
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Mechanical work associated with conversion of floor 3rd-7th to residential use.
INSTALLATION OF 300PSF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE NYC CODE 2022, NO CHANGES IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Structural work associated with conversion of floor 3rd thru 7th to residential use
Development HUB Initial consultation for the subject project was completed on 07/18/2022 at 3:30 pm. Converting floors 3rd-7th to residential use, and accessory bike storage room in the cellar
Sprinkler work associated with conversion of floors 3rd-7th to residential use.
Plumbing work associated with conversions of 3rd-7th floors to residential use
Application filed for facade repairs as per drawings filed herewith. no change to use, egress, or occupancy as a part of this application.
Structural work on interior of building as per plans filed
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
APPLICATION FILED FOR MODIFICATIONS/ADDITIONS TO PLUMBING/SPRINKLER IN THE CELLAR AND ON THE 1ST FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Temporary sprinkler loop as per plans filed. No change in occupancy, use or egress.
APPLICATION FILED FOR INTERIOR REMOVAL OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 4TH, 5TH, & 6TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
APPLICATION FILED FOR INTERIOR REMOVAL OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 7TH FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
APPLICATION FILED FOR INTERIOR REMOVAL OF NON-LOAD BEARING PARTITIONS, CEILINGS, AND FINISHES ON THE 3RD FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.