15 total
REPLACEMENT OF MAIN DRIVE TRACTION SHEAVE AND HOIST CABLES ON ONE(1) 2500LB CAPACITY, 29-FLOOR, 500FPM, PASSENGER ELEVATOR(#7), PURSUANT TO THE SCOPE OF WORK SUBMITTED.(EV005572)
REPLACEMENT OF MAIN DRIVE TRACTION SHEAVE AND HOIST CABLES ON ONE(1) 2500LB CAPACITY, 29-FLOOR, 500FPM, PASSENGER ELEVATOR(#7), PURSUANT TO THE SCOPE OF WORK SUBMITTED.(EV005572)
REVISION TO PERMIT#101003383 CHANGE ELECTRICAL CONTRACTOR TO PROGRESS ELECTRIC COMPANY AND PLUMBING CONTRACTOR TO GREAT LAKES PLUMBING & HEATING
REVISION TO PERMIT#101003383 CHANGE ELECTRICAL CONTRACTOR TO PROGRESS ELECTRIC COMPANY AND PLUMBING CONTRACTOR TO GREAT LAKES PLUMBING & HEATING
REVISION TO PERMIT#101003378 CHANGE ELECTRICAL CONTRACTOR TO PROGRESS ELECTRIC COMPANY AND PLUMBING CONTRACTOR TO GREAT LAKES PLUMBING & HEATING CO
REVISION TO PERMIT#101003378 CHANGE ELECTRICAL CONTRACTOR TO PROGRESS ELECTRIC COMPANY AND PLUMBING CONTRACTOR TO GREAT LAKES PLUMBING & HEATING CO
INSTALLATION OF DATA CAT6 WIRING
INSTALLATION OF DATA CAT6 WIRING
SELFCERT 2019 CBRC: INTERIOR ALTERATIONS TO EXISITNG 2ND FLOOR OFFICE SPACE (SUITE 202) IN AN EXISTING HIGHRISE BUILDING. NO CHANGE TO EXISTING USE. (OCCUPANCY B / CONSTRUCTION TPE 1A)
SELFCERT 2019 CBRC: INTERIOR ALTERATIONS TO EXISITNG 2ND FLOOR OFFICE SPACE (SUITE 200) IN AN EXISTING HIGHRISE BUILDING. NO CHANGE TO EXISTING USE. (OCCUPANCY B / CONSTRUCTION TPE 1A)
MODERNIZATION OF THREE(3) 2500LB CAPACITY, 500FPM, (CARS #4-5) 23-FLOOR, (CAR #6) 22-FLOOR, PASSENGER ELEVATORS, PURSUANT TO THE SCOPE OF WORK SUBMITTED.(EV005572)10100
ERECT ONE SCAFFOLD FRO 04/02/2021 TO 04/02/2022.
ERECT FOUR(4)SCAFFOLDS FROM 03/13/2020 TO 03/13/2021.
REMOVAL/REPLACEMENT OF TERRA COTTA UNITS AS REQUIRED CONCENTRATED AT THE SOUTHWEST & SOUTHEAST 24TH LEVEL CORNERS AND LEVELS 27,38,43, AND 46.
NOT APPLICABLE, PROJECT COMPLETE, SIGN IN PLACE