Support of Excavation for the Installation of Subsurface Stormwater Chambers
SUBSEQUENT FILING FOR PL WORK - STORM/DRAINAGE PIPING, DRAINS, DRYWELL RETENTION.
Infrastructure to improve management of stormwater runoff from the tributary impervious surfaces. On-site Green Infrastructure Cloudburst Pilot Project. DEP Capital Contract No. GQ-H-POMO, Pomonok Houses, NYCHA facility.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 155-11 JEWEL AVENUE, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 155-23 JEWEL AVENUE, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 67-45 KISSENA BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 67-45 KISSENA BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 155-23 JEWEL AVENUE, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 65-10 PARSONS BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 65-10 PARSONS BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Apt 03A — Eviction
INTERIOR RENOVATION OF EXISTING LAUNDROMAT. WORK INCLUDES REPLACE WASHERS AND DRYERS, DRYERS VENT INSTALLATION. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Judgment: NO
Apt 7B — Possession
fire-rated enclosure required - architectural category
IRA for installation of the vertical conduit on the exterior building wall
remove existing gas distribution piping in cellar, and replace with new. abandon existing gas risers in pace and install new exposed gas risers in residential kitchens. extend a collateral extension to existing stoves
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
replacement of all existing gas piping distribution lines, including underground piping in between buildings. installation of new exposed gas risers in residential kitchen, with lateral connections to existing stoves.
Removal of existing gas service pipe mains, and replacement with new. Abandoning of gas risers in place, and installation of new exposed gas risers for residential kitchens.
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
replacement of all existing gas piping distribution lines, including underground. installation of new exposed gas risers in residential kitchen, with lateral connections to existing stoves.
Dish:Install 3 new telecom antenna sectors(1 antenna&3 RRH unit/sector),1 GPS,3 kickbacks&1 equipment cabinet on new platform on roof.Installation conduits&service room connections as plans.All work in compliance w/ 5/98.No change in use,egress&occupancy
Dish-Installation of new telecommunication antenna sectors,kickbacks,GPS&equipment cabinet on new platform on roof.Installation of conduits&service room connection as per plans. All work is in compliance with TPPN5/98.No change in use,egress or occupancy.
replacement of all existing gas piping distribution lines, including underground. installation of new exposed gas risers in residential kitchen, with lateral connections to existing stoves.
FILING HEREWITH PLANS AND APPLICATIONS TO REMOVE FOUR EXISTING 5-TON PACKAGED AC UNITS AND INSTALL 4 NEW PACKAGED AIR-COOLED 5-TON AC UNITS IN PLACE AND RECONNECT TO EXISTING DUCTWORK. ALSO, INSTALL 3 NEW SPLIT AIR-COOLED AC UNITS(HEAT PUMP).
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 155-23 JEWEL AVENUE, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 67-43 KISSENA BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 65-10 PARSONS BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 155-23 JEWEL AVENUE, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 65-10 PARSONS BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 155-11 JEWEL AVENUE, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 67-43 KISSENA BOULEVARD, QUEENS AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INTERIOR RENOVATION OF EXISTING LAUNDROMAT. WORK INCLUDES ONLY REPLACE WASHERS AND DRYERS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
Remove existing gas distribution piping in cellar, replace with new. Abandon existing gas risers in place and install new exposed gas risers in residential kitchens. Lateral connections to existing stoves. Removal and replacement of underground piping.
Remove existing gas distribution piping in cellar, replace with new. Abandon existing gas risers in place and install new exposed gas risers in residential kitchens. Lateral connections to existing stoves. Removal and replacement of underground piping.
Remove existing gas distribution piping in cellar, replace with new. Abandon existing gas risers in place and install new exposed gas risers in residential kitchens. Lateral connections to existing stoves. Removal and replacement of underground piping.
Remove existing gas distribution piping in cellar, replace with new. Abandon existing gas risers in place and install new exposed gas risers in residential kitchens. Lateral connections to existing stoves. Removal and replacement of underground piping.
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
Remove existing gas distribution piping in cellar, replace with new. Abandon existing gas risers in place and install new exposed gas risers in residential kitchens. Lateral connections to existing sloves. Removal and replacement of underground piping.
remove existing gas distribution piping in cellar, replace with new. abandon existing gas risers in place and install new exposed gas risers in residential kitchens. lateral connections to existing stoves. removal and replacement of underground piping
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019