88 total · Page 1 of 5
COMBINE APARTMENTS #720 AND #723 ON THE SEVENTH FLOOR AS PER TPPN 3-97 OF A MIXED USE RESIDENTIAL AND COMMERCIAL BUILDING, AS PER PLANS SUBMITTED. NOT CONSTITUTE ANY CHANGE IN USE, EGRESS OR OCCUPANCY.
Filing for new sprinkler work at the 8th and 9th floor. No change to use, egress, or occupancy.
Filing for new plumbing work at the 8th and 9th floors. No change to use, egress, or occupancy.
Filing for structural work at the 8th and 9th floors. Work includes removal of slab and installation of new convenience stair, framing. No change to use, egress, or occupancy.
Filing for mechanical work at the 8th, 9th floor, and roof. No change to use, egress, or occupancy.
Filing for partial demo (DMO) for the slab opening for new stair associated with structural application #M00959500-S3. No change to use, egress, or occupancy.
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Filing for new plumbing work at cellar. No change to use, egress or occupancy.
Filing combination of unit 801 on the 8th flr & PH3 on the 9 flr to create a duplex apt per TPPN 3/97. Work includes removal & installation of int. non load bearing partitions, doors, finish work, new opening for stair. No change to use, egress, occupancy
INSTALL NEW EXHAUST FAN, MAKE-UP AIR INTAKE FAN, AND ASSOCIATED DUCTWORK FOR LAUNDRY ROOM. NO CHANGE IN MEANS OF EGRESS, USE GROUP, OR OCCUPANCY.
Installation of a suspended scaffold for Facade Inspection and repair as per plan submitted. No change to egress or occupancy.
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of a temporarily shanty per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of temporary material hoist as per plans submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Filing for new plumbing work on the 6th Floor. No change to use, egress, or occupancy.
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
HEREBY FILING FOR THE INTERIOR RENOVATION OF APARTMENT #221 LOCATED ON THE 2ND FLOOR. NO CHANGE TO USE OCCUPANCY OR EGRESS.
HEREBY FILING FOR THE REPLACEMENT, RELOCATION AND INSTALLATION OF FIXTURES IN APARTMENT #221 LOCATED ON THE SECOND FLOOR. NO CHANGE TO USE OCCUPANCY OR EGRESS.
HEREBY FILING FOR THE INTERIOR RENOVATION AND INSTALLATION OF AIR HANDLER IN APARTMENT #301 LOCATED ON THE 3RD FLOOR. NO CHANGE TO USE OCCUPANCY OR EGRESS.
HEREBY FILING FOR THE INTERIOR RENOVATION AND INSTALLATION OF AIR HANDLER IN APARTMENT #422 LOCATED ON THE 4TH FLOOR. NO CHANGE TO USE OCCUPANCY OR EGRESS.