6 total
INSTALLATION OF INDUSTRIAL ROPE ACCESS FOR FACADE INSPECTIONS.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Filing to replace AHU-1 W/dedicated fresh air intake ducting to heat & cool floors 002-031. AHU-1 to provide heat via connection to existing steam & cooling via connection to new water cooled condensers (CU-1, CU-2, CU-3) W/associated piping, & controls.
TEMPORARY PLACEMENT OF TUBULAR STEEL SCAFFOLD STRUCTURE WITH MATERIAL HOISTS AS SHOWN ON PLANS. INSTALLATION SHALL COMPLY WITH BSA-362-44-SM, LL-33/91 AND CHAPTER 33 OF 2014 BC. NO CHANGE IN EGRESS, OCCUPANCY OR USE ASSOCIATED WITH THIS PERMIT.