HEREBY FILING PLUMBING WORK AT 27TH FLOOR UNIT 27H AS PER PLANS
HEREBY FILING PLUMBING WORK AT 23RD FLOOR UNIT 23E AS PER PLANS
HEREBY FILING PLUMBING WORK AT 28TH FLOOR UNIT 28B AS PER PLANS.
HEREBY FILING GENERAL CONSTRUCTION WORK AT 23RD FLOOR UNIT 23E AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
HEREBY FILING GENERAL CONSTRUCTION WOKR AT 28TH FLOOR UNIT 28B AS PER PLANS. NO CAHNGE IN USE EGRESS OR OCCUPANCY.
HEREWITH FILING MECHANICAL WORK AS PER PLANS.
Call
HEREBY FILING GENERAL CONSTRUCTION AT 16TH FLOOR UNIT 16D AS PER PLANS.
HEREBY FILING PLUMBING WORK AT 16TH FLOOR UNIT 16D AS PER PLANS.
HEREWITH FILING PLUMBING WORK AS PER PLANS.
1 infested unit(s) reported
HEREWITH FILING SPRINKLER/STANDPIPE WORK AS PER PLANS.
HEREWITH FILING SPRINKLER/STANDPIPE WORK AS PER PLANS.
HEREBY FILING PLUMBING WORK AT 10TH FLOOR UNIT 10D AS PER PLANS
HEREWITH FILING GENERAL CONSTRUCTION WORK FOR THE AFAM OFFICE RENOVATION AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
HEREBY FILING GENERAL CONSTRUCTION WORK AT 25TH FLOOR UNIT 25A AS PER PLANS
HEREBY FILING GENERAL CONSTRUCTION WORK AT 27TH FLOOR UNIT 27H AS PER PLANS
HEREBY FILING PLUMBING WORK AT 10TH FLOOR UNIT 10B AS PER PLANS
HEREBY FILING PLUMBING WORK AT 24TH FLOOR UNIT 24B AS PER PLANS
HEEREBY FILING GENERAL CONSTRUCTION WORK AT 24TH FLOOR UNIT 24B AS PER PLANS
HEREBY FILING PLUMBING WORK AT 12TH FLOOR UNIT 12D AS PER PLANS
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
MATERIAL ONLY HOISTS AS PER DRAWINGS, DURING BLDG ALTERATION, FILED SEPARATELY. PIPE SCAFFOLD FILED SEPARATELY. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY MONORAIL SYSTEM AS PER DRAWINGS DURING BUILDING ALTERATION, FILED SEP. MONORAIL SYSTEM SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
EQUIPMENT USE: DUAL 7000 # CAPACITY PERSONNEL/MATERIAL HOISTS DURING BLDG ALTERATION, FILED SEP. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY.
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
HEAVY DUTY URBAN SIDEWALK SHED DURING BUILDING ALTERATION, FILED SEP. SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY ROOF PROTECTION DURING BLDG ALTERATION, FILED SEP. ROOF PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BLDG ALTERATION, FILED SEPARATELY. HOIST RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. HOIST & ELEVATOR APPL SUBMITTED SEP
CONSTRUCTION FENCE AS PER DRAWINGS. CONSTRUCTION FENCE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. DOT PERMITS BY OTHERS FOR FENCE INSTALLED ON SIDEWALK/ROADWAY.
HEREBY FILING GENERAL CONSTRUCTION WORK AT 10TH FLOOR UNIT 10D AS PER PLANS
HEREBY FILING GENERAL CONSTRUCTION WORK AT 12TH FOOR UNIT 12D AS PER PLANS
HEREBY FILING GENERAL CONSTRUCTION WORK AT 10TH FLOOR UNIT 10B AS PER PLANS
HEREBY FILING PLUMBING WORK AT 28TH FLOOR UNIT 28H AS PER PLANS
HEREBY FILING GENERAL CONSTRUCTION TO THE 28TH FLOOR UNIT 28H AS PER PLANS
INTERIOR DEMOLITION AS PER PLANS FILED HEREWITH.
HEREBY FILING GENERAL CONSTRUCTION WORK AT 32ND FLOOR UNIT 32A AS PER PLANS. RELATED PLUMBING WORK FILED SEPARATELY
Driver Self Report
IT IS PROPOSED TO REMOVE EXISTING NON LOAD BEARING PARTITIONS DOORS AND FINISHES TO BE REPLACED WITH NEW AS PER PLANS. THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS UNDER THIS APPLICATION
HVAC/DUCTWORK MODIFCATIONS PER PLANS FILED, THERE IS NO CHANGE IN OCCUPANCY USE OR EGRESS UNDER THIS APPLICATION
RENOVATION OF EXISTING HOUSE OF WORSHIP, INT & EXT DEMO, GENERAL CONSTRUCTION. REMOVAL & REPLACEMENT OF EXISTING FACADE INCLUDING ORNAMENTAL TOWER/SPIRE, EXISTING ARCADE & EXTERIOR PLAZAS & ROOF SURFACES. CHANGE TO OCCUPANCY & EGRESS. HUB ACCEPTED 9.7.23
TEMP CONSTRUCTION OFFICE IN ACCORDANCE WITH BC 3303.16.
HEREWITH FILING MECHANICAL WORK AS PER PLANS.
HEREWITH FILING STRUCTURAL WORK AS PER PLANS
HEREWITH FILING FOR FOUNDATION WORK AS PER PLANS
INTERIOR FIT OUT OF STOREFRONT FOR TEMP RELOCATION OF MUSEUM OFFICES, STORAGE AND RECEPTION. APPLICATION FILED IN CONJUNCTION WITH M00930717.
ASSOCIATED MECHANICAL APPLICATION FOR INTERIOR FITOUT FOR TEMPORARY RELOCATION OF MUSEUM OFFICES, STORAGE, AND RECEPTION.
INSTALLATION OF TEMPORARY SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
HEREWITH FILING PLUMBING WORK AS PER PLANS
ASSOCIATED PLUMBING WORK FOR INTERIOR FIT OUT FOR TEMPORARY RELOCATION OF MUSEUM OFFICES, STORAGE AND RECEPTION.