12 total
STRUCTURAL WORK FOR REPAIRS AT FOURTH FLOOR JOIST FRAMING AND NORTH AND SOUTH EXISTING FIRE ESCAPES AT 3RD FLOOR LANDING AS NEEDED.
WORK SHALL INCLUDE DIRECT REPLACEMENT OF FINISHES DIRECT REPLACEMENT OF APARTMENT KITCHEN, BATHROOMS, DOORS AND WINDOW SASHES. ADDITIONAL GROUND LEVEL HARDSCAPE REPAIRS AND IMPROVEMENTS AS NEEDED PER PLANS.
Facade repairs. No change in egress, use or occupancy.
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Suspended scaffold in order to perform exterior facade repairs. Facade inspections to be performed. Material hoist installed. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.
Installation of plumbing fixtures along with related piping.
Scope of work includes the repair and/or replacement of ventilation components and heating elements in bathroom/kitchen of existing apartments, as needed.
Suspended scaffold in order to perform exterior facade repairs. Facade inspections to be performed. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.
Installation of 180LF of sidewalk shed as shown in the plans, it will be no change in the use or occupancy, sidewalk shed to comply with chapter 33 NYC building code.
Suspended scaffold in order to perform exterior facade repairs. Facade inspections to be performed. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.
INSTALL DEBRIS CHUTE AS PER PLANS IN ORDER TO PERFORM FACADE REPAIR. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. DEBRIS CHUTE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE.
Suspended scaffold in order to perform exterior facade repairs. Facade inspections to be performed. Sidewalk shed filed under separate application. No change in use, occupancy or egress under this application.