Filing for repairs to the facades. No change to use, occupancy or egress.
Filing for repairs to the facades. No change to use, occupancy or egress.
Facade Restoration & Inspection
AT&T - Modification to the existing plumbing system, installation of gas piping & gas meter as per plans (10075445 - AT&T). No change to use, egress or occupancy.
AT&T - Modification to the existing HVAC system & installation of non-emergency gas fired generator as per plans (10075445) - Overlay. No change to use, egress or occupancy.
Removal of equipment cabinets as per plans (10075445) - AT&T Overlay. No change to use, egress or occupancy.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
T-Mobile: Installation / replacement of antennas and relocation/removal of RRUs on the roof. Installation/removal of equipment cabinets on the equipment platform on the roof. All work is in compliance with TPPN 5/98. No change in use, egress or occupancy.
Decommission of existing Sprint site. Remove 11 antennas and 9 RRH units from the roof. Service connection in basement. Initial installation approved under application #301354594
DISH-Installation of 3 new antenna sectors including 6 RRH units, 1 GPS unit on roof. Install 1 new equipment cabinet on wall mount. Related service connection inbasement to roof. All in conformance with TPPN 5/98.
AT&T - Replacement of existing antennas on roof. Retrofit of existing cabinets on existing platform on roof. All work in compliance with TPPN 5/98. No change to occupancy, use, or egress.
Modification of existing AT&T site. Replace 6 antenna & 3 RRHs & install 3 RRHs on roof. Replace 1 equipment cabinet & retrofit 1 equipment cabinet on equipment platform on roof. All in conformance with TPPN 5/98. No change in use, egress or occupancy.
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
AT&T / Replacement of existing telecommunications antennas with the replacement/installation of RRH units on roof. Removal and installation of cabinets in the existing equipment platform on roof. All work in compliance with TPPN 5/98. No change to occupancy, use, or egress.