11 total
TEMPORARY STRUCTURE: NEW INSTALLATION. STAGE/PLATFORM - ASSEMBLY - 480 SQ. FT. ELECTRICAL WORK = NO. NON-SEWER TOILETS: 1. INSTALL DATE: 11/21/2025; REMOVAL DATE: 11/22/2025.
TEMPORARY STRUCTURE: NEW INSTALLATION. STAGE/PLATFORM - ASSEMBLY - 480 SQ. FT. ELECTRICAL WORK = NO. NON-SEWER TOILETS: 2. INSTALL DATE: 11/22/2024; REMOVAL DATE: 11/23/2024.
INSTALLATION OF ONE - TEMPORARY 24 X 20 MOBILE STAGE TRAILER (STAGELINE SL 100) FOR CITY OF CHICAGO PRODUCED TREE LIGHTING CEREMONY ON NOVEMBER 17, 2023
INSTALLATION OF ONE - TEMPORARY 24 X 20 MOBILE STAGE TRAILER (STAGELINE SL 100) FOR CITY OF CHICAGO PRODUCED TREE LIGHTING CEREMONY ON NOVEMBER 17, 2023
MODERNIZATION OF ONE(1) 8000LB CAPACITY, 6-FLOOR, PASSENGER ELEVATOR(SERVICE), PURSUANT TO THE SCOPE OF WORK SUBMITTED.(EV007249)DOCK
MODIFICATION TO AN EXISTING CHICAGO APPROVED NON-REQUIRED ADDRESSABLE FIRE ALARM/VOICE EVACUATION SYSTEM TO ACCOMMODATE TENANT RENOVATIONS.
SPR 2019 CBRC - RESTORATION OF STAIN-GLASS DOME, MEP UPGRADES TO GAR ROOM OF EXISTING CULTURAL CENTER AS PER PLANS. STRUCTURAL PEER REVIEW INCLUDED. (OCCUPANCY TYPE: A3; CONSTRUCTION TYPE: 1A)
RELOCATE 4 DATA AND 4 POWER OUTLETS. INSTALL (1) NEW FIXTURE, REMOVE EXISTING.
EXTERIOR FACADE REPAIRS AS PER PLANS
ALL ELEVATIONS, TUCKPOINT 10,000 SQ FT, ONLY
ERECTING 4 SWING STAGE SCAFFOLDS, 04/08/2019 - 04/08/2020