6 total
CONCRETE MASONRY REPAIR / REPLACEMNT: 400SQ. FT., EXCAVATION = NO. LOCATION: PARKING GARAGE LEVELS 5 & 6.
2019 CBC: GARAGE FLOOR REPAIRS AS PER PLANS. NO CHANGE IN USE.
ERECT ONE (1) SCAFFOLD DATES 08/11/2023 THROUGH 08/11/2024
PARKING GARAGE REPAIRS: 430SQFT OF CONCRETE REPAIRS. 300LF OF CRACKS REPAIRS. 1200LF OF SEALANT REPAIRS.
MINOR CONCRETE REPAIR AND COATING ON THE OUTSIDE OF PARKING GARAGE.20 SQUARE FEET.
ERECT TWO SCAFFOLDS FROM 10/09/2020 TO 10/09/2020.