161 total · Page 1 of 9
ILLUMINATED INTERIOR SIGN FACING OUT THE WINDOW; 10 SQ/FT; WINTRUST
ILLUMINATED INTERIOR SIGN FACING OUT THE WINDOW; 10 SQ/FT; WINTRUST
ILLUMINATED INTERIOR SIGN FACING OUT THE WINDOW; 10 SQ/FT; WINTRUST
SELF-CERT 2019 CBRC: INTERIOR ALTERATIONS TO EXISTING 17TH FLOOR OFFICE SPACE. NO CHANGE TO EXISTING USE. (OCCUPANCY B / CONSTRUCTION TYPE 1A)
SC 2019 CBRC: INTERIOR, NON-STRUCTURAL, DEMOLITION OF EXISTING CONDITIONS ON THE 18TH FLOOR. NO CHANGE TO USE OR OCCUPANCY. (OCCUPANY GRP. B; TYPE IA CONSTRUCTION)
FIRE ALARM: REPAIR EXISTING SYSTEM. AFFECTS: 0 DWELLING UNITS; 1 NON-RESIDENTIAL UNITS. HIGH-RISE BUILDING: YES. VOICE COMMUNICATION: YES. SPECIAL LOCKING: YES. MONITORING TYPE: SUPERVISING STATION . SPECIFIC LOCATION: 12TH FLOOR.
FIRE ALARM: MODIFICATION OF EXISTING SYSTEM. ASSOCIATED BUILDING PERMIT:101053255. AFFECTS: 0 DWELLING UNITS; 0 NON-RESIDENTIAL UNITS. HIGH-RISE BUILDING: YES. VOICE COMMUNICATION: NO. SPECIAL LOCKING: YES. MONITORING TYPE: SUPERVISING STATION . SPECIFIC LOCATION: LOWER LEVEL.
LOW VOLTAGE/COMMUNICATION ELECTRICAL WORK. INSTALL DATA/VIDEO. SPECIFIC LOCATION: 12TH FLOOR & LOWER LEVEL.
FOR PERMIT 101053255: REPLACEMENT ELECTRICAL CONTRACTOR. REPLACEMENT PLUMBING CONTRACTOR. NEW CONTRACTOR(S) LISTED UNDER "OTHER APPLICANTS AND CONTRACTORS" ON PERMIT CERTIFICATE.
SPR 2019 CBRC: INTERIOR BUILD-OUT OF NEW FITNESS CENTER THAT INCLUDES NEW RESTROOMS, LOCKER ROOM, FIXED EQUIPMENT, AND RECREATION AREAS IN THE LOWER LEVEL OF EXISTING OFFICE BUILDING AS PER PLANS. (OCCUPANCY GROUP A-3;TYPE 1-A CONSTRUCTION)
SELF-CERT 2019 CBRC: INTERIOR ALTERATIONS TO EXISTING 12TH FLOOR OFFICE SPACE. SCOPE TO INCLUDE REWORKING OF EXISTING ELECTRICAL, MECHANICAL, PARTITIONS, SPRINKLERS AND FINISHES. NO CHANGE TO EXISTING USE. (OCCUPANCY B / CONSTRUCTION TYPE 1A)
PROVIDE AND INSTALL (1) 1-1/4¿ CONDUIT FROM THE 7TH FLOOR SHAFT TO THE C-QUAD TELECOM RISER CLOSET. PROVIDE AND INSTALL (1) 1-1/4¿ CONDUIT FROM THE 21ST FLOOR C-QUAD TELECOM RISER CLOSET TO THE DAS HEADEND ROOM. INSTALL (1) CUSTOMER SUPPLIED FIBER OPTIC CABLE FROM THE 21ST FLOOR DAS HEADEND ROOM TO THE A-LEVEL BASEMENT NORTHWEST CORNER JUNCTION BOX WHERE THE MPOE RESIDES, LEAVING SLACK COILS WITH THE NECESSARY FOOTAGES AT EACH END, FOR TERMINATIONS TO BE COMPLETED BY OTHERS.
HARDWIRE OPEN ARE WORKSTATIONS ON THE 20TH FLOOR, CIRCUITS BY OTHERS.
HARDWIRE OPEN AREA WORKSTATIONS ON THE 19TH FLOOR. CIRCUITS BY OTHERS.
**FIRE ALARM PERMIT**INSTALLATION OF 5 MAGLOCK SYSTEMS AND 27 CARD READER SYSTEMS ON FLOORS 19, 20, AND 23 AS PER PLANS.
TEMPERATURE CONTROL ON THE 19TH FLOOR
TEMPERATURE CONTROL WIRING ON FLOORS LOWER LEVEL 20 AND 23
DEMISING CORRIDOR AND TERRACE LIGHT ON THE 23RD FLOOR
SELF-CERT 2019 CBRC: BUILD OUT OF 23RD FLOOR ROOF TERRACE IN AN EXISTING BUILDING TO INCLUDE NEW PAVERS, RAILINGS & LIGHTING AS PER PLANS. (OCCUPANCY GROUP A-3, CONSTRUCTION TYPE IA) (STRUCTURAL PEER REVIEW)(NO CHANGE IN USE)
REPAIR WATER DAMAGE ON ONE (1) 5000LB.CAP, 200 FPM, 10-STOPS, 9-FLOORS, GEARED TRACTION FREIGHT ELEVATOR #25 INCLUDING NEW COP. DOOR OPERATOR, GOVERNOR CABLE, AND PIT,DIRECTIONAL, FINAL, GATE SWITCHES. PURSUANT TO THE SCOPE OF WORK SUBMITTED. EV003709