200 RIVER ROAD, STATEN ISLAND, NY 10314 · New York City · 3 total events
Con Edison's Goethals Substation - Facility Upgrades. Construct as follows: new pile supported foundations for elec equip supports, new moat and equip pad for a transformer & phase angle regulator, fire rated CMU walls, access stairs. SEE COMMENTS FOR PAA
Installation of foundations for electrical equipment at Con Edison's Goethals Substation. Work to include installation of Helical Piles.
Rebuild concrete transformer pad. Grading as shown. Installation of grounding elements for reactor.