91-03 1/2 139 STREET, Queens, NY, 11435 · New York City · 14 total events
TEMPORARY PLATFORMS CONSTRUCTED FOR OUTDOOR FASHION SHOW EVENT ON SEPTEMBER 14, 2025. THIS EVENT WILL TAKE PLACE IN COLUMBUS PLAZA.
Herewith filing for 1st floor: Installation of new elevator sump pump and drain lines. Condensate drain lines from AC-1 to second floor mop sink.2nd floor: Routh sump and condensate drain lines to discharge at existing mop sink.
1st fl: Install new high temperature limit thermostat & new wall mounted AC unit with condensate lines and liquid and gas piping.2nd fl: Route condensate line from new AC unit to terminate at existing mop sink 3 & 4Route liq.&gas risers from new AC throug
Herewith filing to Replace existing elevator pit ladders with ADA compliant ladders, Construct new 2 hr rated wall assembly, Replace (2) existing doors, and installation of new fire rated access panels as per the drawings. No change in use, egress or occ.
INSTALLATION OF TEMPORARY CONSTRUCTION WOOD FENCE PER PLAN SUBMITTED DURING WORK. THE WORK SHALL COMPLY WITH THE 2014 BUILDING CODE CHAPTER 33.
INSTALLATION OF PLUMBING FIXTURES FOR KIOSK.
INSTALLATION OF AC SPLIT SYSTEM AIR-COOLED AIR CONDITING UNIT, AND KITCHEN HOOD, SUPPLY, RETURN EXHAUST AIR FANS.
ILLUMINATED NON-ADVERTISING ACCESSORY WALL SIGN - IN PROPERTY LINES - GERMAN DONER KEBAB. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
MODIFICATION AND INSTALLATION OF EXISTING FOOD KIOSK INCLUDING FOOTING, FOUNDATION, AND STRUCTURAL WORKS.
MODIFICATION AND INSTALLATION OF EXISTING FOOD KIOSK INCLUDING FOOTING, FOUNDATION, AND STRUCTURAL WORKS.
MODIFICATION AND INSTALLATION OF EXISTING FOOD KIOSK INCLUDING FOOTING, FOUNDATION, AND STRUCTURAL WORKS.
MODIFICATION AND INSTALLATION OF EXISTING FOOD KIOSK INCLUDING FOOTING, FOUNDATION, AND STRUCTURAL WORKS.
MODIFICATION OF EXISTING FOOD KIOSK INCLUDING FOOTING, FOUNDATION, PARTITIONS, AND INTERIOR & EXTERIOR FINISH.
INSTALLATION OF TEMPORARY PLATFORM STAGE AND ASSOCIATED STAIRS FOR BOROUGH PRESIDENT REYNOSO OUTDOOR EVENT.