REPLACEMENT OF TWO CHILLER UNITS ON THE ROOF. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
INSTALLATION OF DAIKIN SPLIT SYSTEM WITH A TOTAL CAPACITY OF 1 TON , LOCATED ON THE GROUND FLOOR AND ROOF.
MECHANICAL WORK CONSISTING MECHANICAL REMOVALS & NEW RTU, FANS, DAMPERS AND ASSOCIATED DUCTS & PIPING TO EXISTING AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
FACADE REPAIRS AND ROOF MEMBRANE REPLACEMENT AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
ROOF PLUMBING WORK FOR NEW RPZ AND ASSOCIATED PIPING FILED IN CONJUNCTION WITH ASSOCIATED MECHANICAL APPLICATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF OVERHEAD PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. PIPE SCAFFOLDING SHALL COMPLY WITH CHAPTER # 33 OF THE CODE, NO CGANGES IN USE IN EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NEEDLE BEAM SHALL COMPLY WITH THE CHAPTER #33 OF THE CODE. NO CHANGES IN USE EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Remove and replace unit for IT room. There is no change in use, egress, or occupancy for this job.