43-01 43 AVENUE, Queens, NY, 11104 · New York City · 43 total events
9th Cycle Facade Inspection & Safety Program. No change to use, egress, or occupancy.
EMERGENCY INSTALLATION OF SIDEWALK SHED AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Suspended scaffold installation as per plans filed herewith.
12TH FLOOR-- MODIFICATIONS TO EXISTING SPRINKLER SYSTEM FOR OFFICE RENOVATIONS.
TEMPORARY PROTECTION STRUCTURE DURING BUILDING SKYLIGHT REMOVAL
Roof replacement per plans filed herewith.
skylight infill as per plans filed herewith
Plumbing modifications and installations for office renovations.
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES WITH RELATED PIPING MODIFICATIONS.
SUITE 401-- MODIFICATION AND INSTALLATION OF PLUMBING FIXTURES FOR OFFICE RENOVATION.
SUITE 401-- GENERAL CONSTRUCTION INCLUSIVE OF INTERIOR PARTITIONS MODIFICATIONS FOR OFFICE RENOVATION. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
SUITE 401-- MODIFICATION TO EXISTING MECHANICAL SYSTEM. INSTALLATION OF NEW HVAC DISTRIBUTION AS PER PLANS.
General construction inclusive of interior demo for pre-tenant white box.
Removal of sprinkler heads and installation of temporary core sprinkler protection for pre-tenant white box.
Replacement of core bathroom fixtures on existing rough and removal of pantry fixtures for pre-tenant white box.
Mechanical duct and equipment demo/modifications for pre-tenant white box.
Modifications to existing sprinkler system for office build-out.
General construction inclusive of modifications to interior partitions.
Mechanical modifications for office pre-tenant renovations.
STRUCTURAL MODIFICATIONS IN CONJUNCTION WITH NEW ACCESS STAIR INSTALLATION.
GENERAL CONSTRUCTION INCLUSIVE OF PARTITIONS MODIFICATIONS, SLAB MODIFICATION FOR ACCESS STAIR INSTALLATION. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
MODIFICATION TO MECHANICAL EQUIPMENT, DUCT, PIPING IN CONJUNCTION WITH OFFICE SPACE RENOVATIONS.
Mechanical modifications in conjunction with new IT room. No change to use, egress or occupancy.
Modifications to mechanical equipment, ductwork, and radiators in conjunction with office suite combination as per plans filed herewith.
Giant Spoon - Structural modifications in conjunction with access stair installation and column reinforcement/intumescent paint application.
Giant Spoon - Install new chilled water unit related duct and equipment for office build-out. Low pressure steam connections for FPB.
T. Rex - Modifications to existing mechanical equipment and duct on part of the 9th floor.
Modification to existing sprinkler system in conjunction with partial 13th floor office build-out.
Modification to mechanical equipment and duct in conjunction with partial 13th floor office build-out.
MECHANICAL DUCT AND EQUIPMENT MODIFICATIONS ON PART OF THE 8TH FLOOR AS PER PLANS FILED HEREWITH.
MODIFICATIONS TO EXISTING SPRINKLER SYSTEM ON PART OF THE 8TH FLOOR AS PER PLANS FILED HEREWITH.
Removal of plumbing fixtures. No change to use, egress or occupancy.
Giant Spoon - Install plumbing fixtures for office build-out.
Installation of ductwork and equipment on part of the 10th floor; connect to existing HVAC. No change to use, egress or occupancy.
Structural support for new operable partition. No change to use, egress or occupancy.
Removal of mechanical equipment and associated ductwork and piping. Install fin-tube radiation system; connect to existing steam risers.
Column reinforcement and intumescent paint applications. Slab in-fill as per plans filed herewith.
T. Rex - Modification to existing sprinkler system on part of the 9th floor.
Giant Spoon - Installation of sprinkler heads; connect to existing system. Install 1 fire hose valve; connect to existing system.
T. Rex - Installation of plumbing fixtures on part of the 9th floor.
Giant Spoon - Installation of sprinkler heads; connect to existing system. Install 1 fire hose valve; connect to existing system.
Installation of plumbing fixtures for 10th floor office pantry.
Installation of sprinkler heads with related piping modifications.