REPLACEMENT OF EXISTING ROOF DRAINS, PIPING, BULKHEAD STORM GUTTER & PIPING WITH NEW AT SAME LOCATIONS ON ROF AS PER PLANS
REPLACEMENT OF EX. MAIN ROOFING SYSTEM, MEMBRANE FLASHING, MAIN ROF PARAPET + BULKHEAD ROF FOR GENERAL BLDG (G) OF NYCCT. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Sidewalk Shed Installation
FILING MODIFICATION TO EXISTING HVAC SYSTEM AND INSTALLATION OF NON REFRIGERANT UNIT AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
REMOVE EX. CTRL VALVE(S) & CHILLED WATER SUPPLY PIPING. FURNISH AND INSTALL NEW PRESSURE INDEPENDENT CONTROL VALVE, ISOLATION VALVE(S) & NEW CHILLED WATER SUPPLY CONNECTIONS TO EX. MH SYSTEM ON 003-006 FLOORS . NO CHANGE IN USE, EGRESS OR OCCUPANCY
INSTALLATION OF NEW SIDEWALK SHED AT 55 JOHNSON STREET, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
NYCCT G-Building, Exterior repairs as per the plans filed including: Removal/replacement/repairs to lintels, cracked/spalled brick masonry, masonry pointing, joint sealant, limestone & terracotta.
INSTALLATION OF PIPE SCAFFOLD AT 55 JOHNSON STREET, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY FENCE TO STORE THE EQUIPMENT. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Herewith Filing to replace the existing standalone air handling unit and associated equipment's as per plans.