Interior demolition of non load bearing partitions on the 9th floor as indicated on drawings
DIRECT REPLACEMENT OF (6) EXISTING 15 TON INDOOR VERTICAL PACKAGE AIR CONDITIONING UNITS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
New partitions and new dropped ceiling at office space.
Modifications to existing LL provided wet system to accommodate the proposed architectural layout. Installation of new plumbing fixtures for the restrooms, janitors closet and kitchen area.
Modifications to existing LL provided wet system to accommodate the proposed architectural layout. Installation of new plumbing fixtures for the restrooms, janitors closet and kitchen area.
Ductwork distribution from two existing LL provided AC units. Toilet exhaust ductwork with inline exhaust fan tying into LL provided exhaust riser. Air-cooled split system for the server room.
DIRECT REPLACEMENT OF (2) EXISTING 15 TON INDOOR VERTICAL PACKAGE AIR CONDITIONING UNITS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INTERIOR DEMOLITION OF NON-LOAD BEARING PARTIONS ON THE 6TH, 7TH AND 8TH FLOORS AS INDICATED ON DRAWINGS.
Restoration and repair of facade as shown on plans. No change in use, occupancy or egress.
Interior demolition of non load bearing partitions on the 4th floor as indicated on drawings.
INSTALL LOUVER FOR BOILER ROOMS AS PER PLANS.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. LIVE LOAD 300 PSF
Mechanical work in conjunction with renovation of existing office space. on the 5th Floor. Install VAV boxes. New Exhaust fan, diffusers and Flow bar. all to any existing Mechanical system with no work to the Existing Air conditioning units.
in conjunction with interior renovation of existing office space. on the 5th Floor. Very minor Structural work for the Hung partition. framing work only
DIRECT REPLACEMENT OF (2) EXISTING 15 TON VERTICAL PACKAGE AIR CONDITIONING UNITS. RECONNECT TO EXISTING DUCTWORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
DIRECT REPLACEMENT OF (2) EXISTING 15 TON VERTICAL PACKAGE AIR CONDITIONING UNITS. RECONNECT TO EXISTING DUCTWORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
In conjunction with interior renovation of existing office space on the 5th floor. sprinkler work to the existing sprinkler system.
In Junction with interior renovation of existing office space on the 5th floor. Plumbing work only.
Modification to existing Plumbing fixtures as per plans filed herewith
Modification to existing Plumbing fixtures as per plans filed herewith
Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
SPLIT UNITS FOR 7TH, 8TH, 9TH FLOOR TENANTS COMPUTER ROOMS AND CONFERENCE ROOM. OBTAIN CERTIFICATE OF COMPLIANCE. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.