Alteration/modification to existing Sprinkler/Fire Protection System. No change in use, egress, or occupancy.
Alterations/modification to existing Mechanical Systems. No change in use, egress, or occupancy
Interior demolition of non-structural partitions , removal of finishes throughout
Alterations/modifications to existing Plumbing System. No change in use, egress, or occupancy..
HVAC unit replacement on the second floor MER. No change in use egress and occupancy.
INSTALLATION OF TEMPORARY SPRINKLER LOOP ON THE 3RD FLOOR. NO CHANGE TO USE, EGRESS AND/OR OCCUPANCY.
REPLACEMENT OF EXISTING PACKAGED AC UNIT IN ACCORDANCE WITH THESE PLANS.
Plumbing demolition
Mechanical demolition
REMOVAL OF INTERIOR NON STRUCTURAL TEMANAT FIT OUT INCLUDING HUNG CEILINGS CABINETRY FLOOR AND WALL FINISHES. FIRE ALARM DEVICES WILL REMAIN . FOR REMOVAL OF MECHANICAL ELECTRICAL PLUMBING & SPRINKLER REFER TO ENGINEERING DRAWINGS .
Installation of sprinkler temporary loop on the 4th floor as per the filed drawings. No change to use, occupancy or egress.
Alterations/modifications to existing plumbing system. No change in egress, use, or occupancy.
Alterations/modifications including interior buildout of a new suite for an existing tenant. Interior renovation of a portion of the 7th consisting of new construction, furniture, equipment, & finishes. No changes in use, egress, or occupancy.
Alterations/modification to existing sprinkler system. No change in use, egress, or occupancy.
Installation of medium pressure ductwork, VAV terminal boxes, low pressure ductwork, ventilation ductwork, environmental exhaust ductwork, DDC controls, precision computer room AC units for Information technology rooms & UPS equipment, supplemental AC
Alterations/modification to existing Mechanical Systems. No change in use, egress, or occupancy
Alteration/modification to existing Sprinkler/Fire Protection System. No change in use, egress, or occupancy.
Alteration/modification to existing Sprinkler/Fire Protection System. No change in use, egress, or occupancy.
Alterations/modifications including restoration of existing restroom on the Cellar & 2nd Floor; removal of existing showers on the 2nd floor; and replacement of all plumbing fixtures and partitions. No change in use, egress, or occupancy.
Alterations/modifications to existing Plumbing System. No change in use, egress, or occupancy..
Alteration/modification to existing Mechanical System. No change in use, egress, or occupancy.
Alteration/modification including construction of a single occupant restroom consisting of 1 water closet & 1 lavatory. No change in use, egress, or occupancy
Alteration/modification of existing Plumbing System. No change in use, egress, or occupancy
Removal of non load bearing partitions as per plans filed herewith.
Removal of AC units and HVAC ductwork and units as per plans.
Modification of the existing sprinkler system on the 1st floor. No change to use, occupancy or egress.
INSTALLATION OF TEMPORARY BETAMAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Alterations/modifications to existing plumbing systems and related piping and ducts. No change in use, egress, or occupancy.
Installation/Infill of structural floor slab. No change in use, egress, or occupancy
Alterations/modification to existing sprinkler systems including removal of pre-action sprinkler system
Tenant alterations to commercial interior including modification/ removal of open staircase, ADA/ Gender Neutral Restrooms, and IDF equipment. Roof scope includes screen wall, dunnage, and roofing path. No change in use, egress, or occupancy.
Alterations/modification to existing MS system. No change in use, egress, or occupancy.
Exterior Modification including sidewalk replacement and concrete repairs to the first floor and basement level of the building. NO CHANGE TO USE, EGRESS, OR OCCUPANCY
Removal of ductwork as per plans filed herewith.
Removal of plumbing fixtures as per plans filed herewith.
REMOVAL OF NON-LOAD BEARING PARTITIONS, SOUND STUDIOWALLS, DOORS, RAISED FLOORS, FLOOR FINISHES, CEILINGS ANDALL ASSOCIATED SUPPORTS
Installation of temporary sprinkler loop on the 7th floor as per plans. No change to use, occupancy or egress.
Exterior Modification including sidewalk replacement and concrete repairs to the first floor and basement level of the building. NO CHANGE TO USE, EGRESS, OR OCCUPANCY
Modification to existing Plumbing fixtures as per plans filed herewith. No change to use, egress or occupancy.
New steel canopy over the main building entrance, reworking of non-structural topping slab in lobby, and coord. with new storefront support at main entrance. No change in egress, use, or occupancy.
Filing for replacement of existing storefront in kind and renovation of existing lobby as shown on plans filed herewith. No change in use, egress, or occupancy.
ductwork and air outlet relocations. Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
Filing for general construction of interior partitions and doors as per plans filed herewith. No change in use, egress, or occupancy.
APPLICATION FILED FOR MODIFICATIONS/ADDITIONS TO MECHANICAL ON THE 2ND FLOOR AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
Modification to existing Sprinkler system as per plans filed herewith. No change in use, egress, or occupancy.
INSTALLATION OF TEMPORARY WORK PLATFORM AS PER DRAWINGS. WORK PLATFORM SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.