248 WEST 35 STREET, Manhattan, NY · New York City · 19 total events
CONVERSION OF AN EXIST. COMMERCIAL FLOOR( 10TH. FLOOR) TO RESIDENTIAL USE AS PER ARTICLE 7B OF MDL.
ENTIRE BUILDING
Judgment: NO
INSTALL PLUMBING FIXTURES FOR FIVE(5) NEW APARTMENTS.
(A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS.
CONVERSION OF AN EXIST. COMMERCIAL FLOOR( 16TH. FLOOR) TO RESIDENTIAL USE AS PER ARTICLE 7B OF MDL.
MOLD
SLOW LEAK
INSTALL EIGHT (8) NEW BATH ROOMS , EIGHT NEW KITCHENS WITH EIGHT NEW ELECTRIC WATER HEATERS FOR EIGHT (8) NEW APARTMENTS ON THE 8TH. FLOOR.
CONVERSION OF AN EXIST. COMMERCIAL FLOOR( 8TH. FLOOR) TO RESIDENTIAL USE AS PER ARTICLE 7B OF MDL.
INSTALL EIGHT (8) NEW BATH ROOMS , EIGHT NEW KITCHENS WITH EIGHT NEW ELECTRIC WATER HEATERS FOR EIGHT (8) NEW APARTMENTS ON THE 4TH. FLOOR.
CONVERSION OF AN EXIST. COMMERCIAL FLOOR( 4TH. FLOOR) TO RESIDENTIAL USE AS PER ARTICLE 7B OF MDL.
INSTALL EIGHT (8) NEW BATH ROOMS AND EIGHT NEW KITCHENS FOR EIGHT (8) NEW APARTMENTS ON THE 7TH. FLOOR.
CONVERSION OF AN EXIST. COMMERCIAL FLOOR( 7TH. FLOOR) TO RESIDENTIAL USE AS PER ARTICLE 7B OF MDL.
MODIFICATIONS TO EXISTING VERIZON SITE. NEW STEEL PLATFORM WITH (3) CABINET INSTALLS. REPLACE (1) ANTENNA & (5) RRH UNITS. INSTALL (5) ANTENNAS & (4) RRH UNITS. REMOVE (2) CABINETS & (5) RRH UNITS. INSTALL (4) MICROWAVE DISHES.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
Replacement of 2 existing 5 tons each split Cooper and Hunter AC units with new ones, Model CH-60LCU/0, serial numbers 240424193087 & 220160012 at second floor as per plans. No change to existing occupancy use or egress.
Modification to existing VERIZON telecommunications site. Replace 3 antennas on the roof. All work in conformance with TPPN#5/98. No change in use, egress, or occupancy.
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE