2462 2 AVENUE, Manhattan, NY, 10035 · New York City · 10 total events
SUSPENDED SCAFFOLD OUTRIGGER SYSTEM FOR THE RESTORATION WORK AT 1118 GRAND CONCOURSE, BRONX, NY 10456.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Bx Courthouse, exterior facade repairs: Removal/replacement/repairs of cracked masonry & glass units, cracked/spalled concrete, stone, stucco and spandrel beams/balconies. Scraping & painting of existing steel lintels/spandrels beams. Various Re-pointing.
APARTMENT ONLY
INSTALLATION OF SUSPENDED SCAFFOLD FOR FACADE INSPECTIONS. SUSPENDED SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
ENTIRE BUILDING
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AND 600 LB. CAPACITY PORTABLE MATERIAL HOIST AS PER PLANS. PIPE SCAFFOLD AND MATERIAL HOIST SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER PLANS. TEMPORARY DEBRIS CHUTE SHALL COMPLY WITH CHAPTER #33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019