230 CENTRAL PARK WEST, Manhattan, NY, 10024 · New York City · 38 total events
PLUMBING FILED IN CONJUNCTION WITH COMBINATION OF APTS 9K & 9L. INSTALL PLUMBING FIXTURES AND RELATED PIPING. CAP/REMOVE FORMER KITCHENETTE IN APT 9L.
COMBINE APTS. 9K & 9L IN ACCORDANCE WITH TPPN3/97. INTERIOR DEMO & CONSTRUCTION OF NON-STRUCTURAL PARTITIONS, FIXTURES AND FINISHES. MINOR MECHANICAL WORK TO RECONFIGURE EXISTING TOILET EXHAUST DUCTWORK. NO CHANGE TO USE EGRESS, OR OCCUPANCY.
Modifications to existing Plumbing Fixtures (APT 3CD) as per plans filed herewith. No change in use, egress or occupancy.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
Interior renovations as per drawings filed herewith (Apt 3CD). No change to use egress or occupancy.
Limited Exterior and Roof Level Repair Program; No change to Use, Egress or Occupancy.
INSTALLATION OF OUTRIGGERS FOR FACADE REPAIR AND INSPECTION
§27-2107 ADM CODE OWNER FAILED TO FILE A VALID REGISTRATION STATEMENT WITH THE DEPARTMENT AS REQUIRED BY ADM CODE §27-2097 AND IS THEREFORE SUBJECT TO CIVIL PENALTIES, PROHIBITED FROM CERTIFYING VIOLATIONS, AND DENIED THE RIGHT TO RECOVER POSSESSION OF PREMISES FOR NONPAYMENT OF RENT UNTIL A VALID REGISTRATION STATEMENT IS FILED.
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Installation of plumbing fixture as plans
Renovation of apartment 15A, No change in use egress or occupancy.
Mechanical related work in conjunction with Apartment 16ABCM renovations including installation of HVAC units
PLUMBING WORK AT APARTMENT 8KL AT EIGHT FLOOR. REPLACING EXISTING BATHROOM FIXTURES AT THE SAME ROUGHING. REPLACING KITCHEN CABINETS AS PER PLANS.NO CHANGE OF USE, OCCUPANCY,EGRESS OR C.O IS PROPOSED UNDER THIS APPLICATION
PLUMBING WORK OF APARTMENTS 8J AND 9J. NO CHANGE INS USE, EGRESS, OR OCCUPANCY.
INTERIOR RENOVATION OF APARTMENT 8KL AT EIGHT FLOOR. REPLACING EXISTING BATHROOM FIXTURES AT THE SAME ROUGHING. REPLACING KITCHEN CABINETS, REPLACING FLOOR FINISHES AS PER PLANS.NO CHANGE OF USE, OCCUPANCY,EGRESS OR C.O IS PROPOSED UNDER THIS APPLICATION
GENERAL CONSTRUCTION, PLUMBING, AND STRUCTURAL WORK TO COMBINE UNITS 8J & 9J. APARTMENTS COMBINED PER TPPN 3/97. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
STRUCTURAL WORK FOR NEW STAIR OPENING IN APT 9J ON 9TH FLOOR AND NEW STAIR BETWEEN APTS 8J & 9J. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
INTERIOR COMBINATION AND RENOVATION OF APARTMENTS 12-H & 12-I WITH RELATED MECHANICAL WORK ASPER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
PLUMBING WORK TO ACCOMMODATE RENOVATION TO APARTMENTS 8A-8M AS PER PLANS FILED HEREWITH.
INSTALLATION OF MECHANICAL SYSTEM IN APARTMENT 16K. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
New AC split system unit
PLUMBING WORK IN APT 2C ON THE SECOND FLOOR. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Interior renovation of apartment 16K on the 14th and 15th floor.
MODIFICATION OF PLUMBING WORK ASSOCIATED WITH RENOVATION OF BATHROOM IN APT 2K AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
MODIFICATION OF PLUMBING WORK ASSOCIATED WITH RENOVATION OF BATHROOM IN APT 2K AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
PLUMBING WORK ASSOCIATED WITH THE INTERIOR COMBINATION AND RENOVATION OF APARTMENTS 12-H & 12-I AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
INTERIOR COMBINATION AND RENOVATION OF APARTMENTS 12-H & 12-I WITH RELATED MECHANICAL WORK ASPER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
MINOR INTERIOR ALTERATION, NO CHANGE TO USE, OCCUPANCY OR EGRESS
plumbing work
INTERIOR PLUMBING WORK IN APARTMENT 16K. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Structural related work in conjunction with Apartment 16ABCM renovations.
PLUMBING WORK IN APT 2M IN CONJUNCTION WITH DOB HUB FILING. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Remove and replace two through wall ac units in apartments 8A-8M as per plans.
Respectfully Request to File for Capping & Removing of Plumbing Work. All Work was done under DOB # 110114064 which was reinstated for sign-off. No approved plans exist with DOB nor Original Applicant of Record.
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION. NO CHANGE IN USE,EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
INSTALLATION OF A TEMPORARY SCAFFOLD AS PER PLANS IN CONJUNCTION WITH GENERAL CONSTRUCTION. NO CHANGE IN USE,EGRESS OR OCCUPANCY. SCAFFOLD SHALL COMPLY WITH 2014 NYC BUILDING CODE, CHAPTER 33.
Installation of a new split-type AC system for the Round Room.
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.