2139 1 AVENUE, Manhattan, NY, 10029 · New York City · 27 total events
APARTMENT ONLY
SOE work at Columbia University Irving Medical Center Allen Rosenfield Building - North Vault Shoring- Vault Walls at Boring Infill work as per plans filed herewith.
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY SIDEWALK SHED/STORAGE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
INSTALLATION OF MATERIAL ONLY HOISTS AS PER DRAWINGS. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Filing to show existing plumbing fixtures as installed by DASNY prior to CUMC ownership. work performed under job 104264207 and 103955506
Installation of suspended scaffold during facade inspection/ repair and hoist.
FACADE RESTORATION FOR CYCLE 9A, WINDOW REPLACEMENT AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY STORAGE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY
SUBSEQUENT APPLICATION FILED SPRINKLER AND PLUMBING WORK AT BIO BANK. PIPE WORK TO SUPPORT INSTALLATION OF LIQUID NITROGEN TANK & NOVAC SYSTEM AS PER PLAN. NO CHANGE TO USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
Application filed for interior partitions, ceiling, doors, walls, floors, Patch/repair, exterior windows at Bio Bank as per plan. No change to egress, use or occupancy
SUBSEQUENT APPLICATION FILED SPRINKLER AND PLUMBING WORK AS PER PLAN. THERE IS NO CHANGE TO USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
SUBSEQUENT APPLICATION FILED TO INSTALL MECHANICAL UNITS AT BIO BANK AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
interior build out of walls, doors, slab, stair relocation, partition, millwork
SUBSEQUENT APPLICATION FILED TO INSTALL MECHANICAL UNITS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
SUBSEQUENT APPLICATION FILED SPRINKLER AND PLUMBING WORK AS PER PLAN. THERE IS NO CHANGE TO USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
SUBSEQUENT APPLICATION FILED SPRINKLER AND PLUMBING WORK AT BIO BANK. PIPE WORK TO SUPPORT INSTALLATION OF LIQUID NITROGEN TANK & NOVAC SYSTEM AS PER PLAN. NO CHANGE TO USE, EGRESS OR OCCUPANCY FILED UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Application filed for framing, new dunnage, slab as per plan. No change to egress, use or occupancy
INSTALLATION OF 300 psf SIDEWALK SHED AND OVERHEAD PROTECTION AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
plumbing and sprinkler modification
REMOVAL OF PARITITION FOR ASSESSORY LOUNGE
LOBBY & STUDENT LOUNGE RENOVATION removal and installation of air handling unit and radiators
plumbing and sprinkler modification
FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09
FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09
installation of a temporary construction fence at public plaza