1910 1 AVENUE, Manhattan, NY, 10029 · New York City · 29 total events
interior renovation to interior pharmacy department, non-structural metal stud walls, millwork, floor, wall and ceiling finishes to enlarge Rx department. Replace water closet for ada at same connection. Insulate lavatory drain pipe. Relo (2) registers
Plumbing subsequent application of the 1st floor for retail build out. No change in use, egress or occupancy
Mechanical renovation of the 1st floor for retail build out. No change in use, egress or occupancy
Renovation of the 1st floor for retail build out, minor partition work, replace wall finishes, floor and ceiling. Subsequent filings for plumbing & mechanical to be filed. No change in use, egress or occupancy
Self Service
Installation of suspended scaffold for facade inspection/repair.
FACADE REPAIR. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
PROPOSED RENOVATION AT EXISTING COMMERCIAL SPACE FOR AN EATING & DRINKING ESTABLISHMENT AT THE FIRST FLOOR LEVEL. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
Alteration of Non Load Bearing Partitions, revise Ceiling tiles layout and remove exiting light fixtures to replace with LED lights in existing office space as per plans filed. No change in Use Occupancy or Egress
INSTALLATION OF NEW SPRINKLERS FOR MINOR RENOVATION AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
ALTERATION OF EXISTING HVAC SYSTEM FOR MINOR RENOVATION AS PER PLANS. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
MINOR RENOVATION OF 4TH FLOOR OFFICE SPACE AS PER PLANS. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
FILING FOR REPLACEMENT OF EXISTING ROOFTOP CONDENSING UNITS AS PER PLANS SUBMITTED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
PROPOSED INTERIOR CONSTRUCTION OF 47SF OF ENCLOSED PHONE BOOTH ON FLOOR 4. SCOPE TO INCLUDE THE CONSTRUCTION OF NEW NON-STRUCTURAL INTERIOR PARTITIONS AS NOTED ON DRAWINGS. NEW LIGHTING FIXTURES ARE TO BE INSTALLED AT THE EXISTING SWITCH LOCATION.
Installation of plumbing fixtures on part of the 4th floor as per plans filed.
Modification to existing sprinkler system on part of the 4th and 10th floors.
General construction inclusive of installation of interior partitions on part of the 4th and 10th floors. No change to use, egress or occupancy.
Mechanical modifications on part of the 4th and 10th floors as per plans filed.
Install new duct and mechanical equipment; connect to existing HVAC.
Replacement of (1) rooftop AC unit on the 3rd floor roof.
Modifications to existing sprinkler system for office build-out.
Installation of plumbing fixtures for office build-out.
Modification to existing sprinkler system; demolition of existing system back to FCVA; installation of required TCSP as required.
LL Pre-tenant Work - Modifications to existing 4th floor duct and equipment in conjunction with tenant space creation. No change to use, egress or occupancy.
Modification to plumbing fixtures as per plans filed herewith.
IN-KIND REPLACEMENT OF GAS PIPING FROM THE EXISTING SHUT-OFF VALVE TO THE REPLACED ROOF TOP HVAC UNIT WHICH WAS FILED UNDER A SEPARATE APPLICATION .
IN-KIND REPLACEMENT OF A ROOF TOP HVAC UNIT. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
FAILED TO FILE FISP CYCLE 8B TECHNICAL REPORT BY 02/21/2018