15 WEST 63 STREET, Manhattan, NY, 10023 · New York City · 13 total events
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SIDEWALK SHED AT THE FRONT OF THE BUILDING, WEST 63RD STREET, AND WEST NEIGHBOR GARAGE RAMP ELEVATION.
0 infested unit(s) reported
ALTERATION TYPE II: RELOCATION OF SPRINKLER HEADS ON EXISTING SYSTEM, ALL ON 37TH FLOOR OF 15 WEST 63RD STREET, AS PER ATTACHED PLANS. NO CHANGE IN USE, EGRESS, FLOOR AREA, VOLUME OR FIRE SAFETY.
FACADE REPAIR ON AN EXISTING BUILDING. NO CHANGE IN USE, OCCUPANCY, OR EGRESS.
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE PIPE SCAFFOLD AT THE SOUTH (WEST 63RD ST) AND WEST ELEVATIONS FROM THE TOP OF THE SIDEWALK SHED TO PAST THE 5TH FLOOR TERRACE.
INSTALLATION OF TEMPORARY WORK PLATFORM AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE WORK PLATFORM ON THE 17TH FLOOR AT THE SOUTHEAST CORNER ALLOWS CUSTOMERS TO LAND THE SUSPENDED SCAFFOLD ON TOP.
INSTALLATION OF TEMPORARY ROOF PROTECTION/OVERHEAD PROTECTION AS PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE ROOF PROTECTION AND OVERHEAD PROTECTION AT THE EAST NEIGHBOR'S ROOF. THE OVH OVER THE MECHANICAL UNITS CONSISTS OF PIPE SCAFFOLD FRAMES.
Application for the installation and use of suspended scaffold as per plans filed herein. No change in egress, use, or occupancy.
ALTERATION TYPE II: REPLACEMENT AND INSTALLATION OF NEW PLUMBING FIXTURES ON 37TH FLOOR OF 15 WEST 63RD STREET, AS PER ATTACHED PLANS. NO CHANGE IN OCCUPANCY, USE, EGRESS, FLOOR AREA, VOLUME OR FIRE SAFETY.
ALTERATION TYPE II: REPLACEMENT AND RELOCATION OF HVAC EQUIPMENT AND DUCTWORK, ALL ON 37TH FLOOR OF 15 WEST 63RD STREET, AS PER ATTACHED PLANS. NO CHANGE IN USE, EGRESS, FLOOR AREA, VOLUME OR FIRE SAFETY
ALTERATION TYPE II: RELOCATION AND REPLACEMENT OF NON-LOAD BEARING PARTITIONS AND CEILINGS, ALL ON 37TH FLOOR OF 15 WEST 63RD STREET AS PER ATTACHED PLANS. NO CHANGE IN OCCUPANCY, USE, EGRESS, FLOOR AREA, VOLUME OR FIRE SAFETY.
SCOPE OF WORK INCLUDES RENOVATING THE POWDER ROOM, BATHROOM # 2 AND CREATING A WINE WALL. NO CHANGE IN USE, OCCUPANCY OF EGRESS.
Replace existing HVAC on roof and all related ductwork/piping on 11-40 floors as per plans. No change in use, egress, or occupancy.