144REAR LUDLOW STREET, Manhattan, NY 10002 · New York City · 218 total events
Feedwater Pump FWS-PB Electric Drive Modification
New sprinkler heads and plumbing fixtures in the Delor lab at Havemeyer building
0 infested unit(s) reported
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLDING. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF NYCC
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLDING. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF NYCC
Devarakonda Lab. Interior renovations as per plans, no change in use, egress or occupancy.
ROOM 916: BRENT STOCKWELL LAB RENOVATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
Devarakonda Lab renovations. Ductwork and associated piping work as per plans filed herewith.
ROOM 916: BRENT STOCKWELL LAB RENOVATION - MODIFICATIONS TO MECHANICAL SYSTEM AS PER PLANS.
Refurbishment of the existing Heating and Ventilation (H&V) Units within the boiler plant. There are five (5) H&V Units in total. The project also includes the replacement of one (1) exhaust fan.
INTERIOR RENOVATIONS INCLUDING DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS, DOORS AND INTERIOR FINISHES, CONSTRUCTION OF NEW NON-LOAD BEARING PARTITIONS, DOORS, AND NEW LIGHTING. NO CHANGE OF USE, EGRESS
Modification of the existing sprinkler system as per the filed plans. No change to use, occupancy or egress.
ROOM 916: BRENT STOCKWELL LAB RENOVATIONS - PLUMBING WORK AS PER PLANS.
Devarakonda Lab renovations. Modifications to existing sprinkler system as per plans filed herewith.
Facade repairs (FISP)CYCLE 9 as per plans. No change to use, egress or occupancy.
GENERAL CONSTRUCTION TO DODGE HALL - AEROBICS ROOM AT FIRST FLOOR AS PER PLANS FILED HEREWITH.
Facade repairs (FISP)CYCLE 9 as per plans. No change to use, egress or occupancy.
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of material hoist
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE.LIVE LOAD 300PSF.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE.LIVE LOAD 300PSF.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE.LIVE LOAD 300PSF.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE.LIVE LOAD 300PSF.
Facade repairs (FISP)CYCLE 9 as per plans. No change to use, egress or occupancy.
Facade repairs (FISP)CYCLE 9 as per plans. No change to use, egress or occupancy.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
INTERIOR PLUMBING WORK AS SHOWN HEREWITH. NO CHANGES TO EGRESS, OCCUPANCY OR USE.
PLUMBING WORK AS SHOWN HEREWITH. NO CHANGES TO EGRESS, OCCUPANCY OR USE.
MECHANICAL WORK ON LEVEL 400 (1ST FL) AND 500 (MEZ1) AS SHOWN HEREWITH. NO CHANGES TO EGRESS, OCCUPANCY OR USE.
INTERIOR RENOVATIONS INCLUDING DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS, DOORS AND INTERIOR FINISHES, CONSTRUCTION OF NEW NON-LOAD BEARING PARTITIONS, DOORS, AND NEW LIGHTING. NO CHANGE OF USE, EGRESS
FILING FOR MECHANICAL WORK AS SHOWN HEREWITH. NO CHANGES TO EGRESS, OCCUPANCY OR USE.
Temporary tents master site plan, no alt to exist structures for West Campus Special Event Program, Various Setups and Dates. TPA permit(s) required for each event. Producer responsible to monitor site safety & implement HWAP.
Installation of outriggers for facade repair and inspection
This application is filed for Domestic Cold Water Feed System Replacement in cellar level.
This application is filed to remove and replace the existing fuel oil line.
This application is filed to remove and replace the existing fuel oil line.
Modification of the sprinkler system to remove and install new sprinkler heads as shown on the drawings filed herewith. No change in use, egress, or occupancy.
installation of plumbing fixtures along with related piping.
Modification of the plumbing system as shown on the drawings filed herewith. No change in use, egress, or occupancy.
REMOVAL AND REPLACEMENT OF LOADING DOCK RAMP IN ENGINEERING LABORATORY BUILDING AS SHOWN ON DRAWINGS SUBMITTED HEREWITH.
Replacement of 50 gallon day tank with 275 gallon day tank on 2nd floor.
Installation of a temporarily heavy-duty sidewalk and construction fence per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application
Installation of a temporarily heavy-duty sidewalk and construction fence per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application
Modification of the mechanical system to remove and install equipment and associated ducts and piping as shown on the drawings filed herewith. No change in use, egress, or occupancy. Replacement of some lighting fixtures as part of work in mechanical room
Replacement of 50 gallon day tank with 275 gallon day tank on 2nd floor.
Replacement of 2000 gallon tank with 2800-gallon day tank.
Renovation, interior construction work as per plans filed herewith. No change of use, occupancy, or egress as of right.
INTERIOR PLUMBING AS SHOWN HEREWITH. NO CHANGE TO EGRESS, OCCUPANCY OR USE