INTERIOR TENANT IMPROVEMENT OF RETAIL SALES (Accessories) AREAS LOCATED AT FIRST LEVEL. SCOPE INCLUDES NEW PARTITIONS, CEILINGS, FINISHES,SHELVING UNITS, No change in use, egress or occupancy
STRUCTURAL DESIGN OF LIGHT GAGE FRAMING FOR NEW FITOUT.
INSTALLATION OF DUCTWORK DISTRIBUTION SYSTEMS Accessories ANDINSTALLATION OF NEW AS SPECIFIED ON PLANS HEREIN.
Modification of sprinkler system as shown on plans
Modification of sprinkler system on part of the 5th floor
THIS PROJECT CONSISTS OF THE INTERIOR RENOVATION OF AN EXISTING RETAIL SPACE WITH NEW SPRINKLER BRANCHES AND RELOCATION OF EXISTING SPRINKLER HEADS CONNECTING TO EXISTING MAIN BUILDING SPRINKLER SYSTEM AS SPECIFIED ON PLANS HEREIN
Modification of sprinkler, standpipe and plumbing systems on 4th floor
Modification of sprinkler, standpipe and plumbing systems on 4th floor
Interior Gut and renovation of the 4th floor. No changes to use, egress or occupancy.
Structural modifications. New openings in existing masonry walls & installation of new steel for new openings. There is no change in use or occupancy.
This project consists of the interior renovation of an existing retail space with installation of new supply ducts connecting to existing main building supply ducts as specified on plans herein
This project consists of the interior renovation of an existing 509 sq.ft space and includes reconfiguration of interior walls and installation of new equipment and fixtures as defined in nyc building code - level type 2 alterations
Modification of HVAC systems on 4th Floor (no separate hvac units- only fan power boxes)
modification to sprinkler system on the arcade level as shown on plans
Installation of temp facade exhibit.no alteration to exist structures for the Temporary Facade Exhibit Installation. Producer is responsible to monitor site safety & implement HWAP. All production equipment removed upon event completion
mechanical modifications to arcade level as shown on plans
Partial interior renovation of the existing 5th floor retail space.
Modification of HVAC system on part of the 5th floor.
Interior renovation on part of the 1st floor as indicated on attached plans.
Sprinkler modification to Chanel space as indicated on attached plans.
INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLD EQUIPMENT.
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Interior remodel of an existing department store. This remodel does not affect the existing building structure, egress requirements or occupant loads.
Installation of new chilled water fan coil unit.
STRUCTURAL DESIGN OF NEW STAIR AND SUPPORT OF NEW STAIR
Interior renovation of Chanel as indicated on the attached plans.
8823 - Modification of Sprinklers in Prada Beauty space. No change in egress, use, or occupancy.
Removal of slab on 4th & 5th floor for future conversion of stairs.
Interior removals for future tenant upgrade.
mechanical modifications as indicated on attached plans
Sprinkler & standpipe modifications on 4th & 5th floor as per attached plans
Sprinkler & standpipe modifications on 4th & 5th floor as per attached plans
Installation of temp facade exhibit.no alteration to exist structures for the Temporary Facade Exhibit Installation. Producer is responsible to monitor site safety & implement HWAP. All production equipment removed upon event completion
RELOCATION OF EXISTING SPRINKLER HEADS TO ACCOMMODATE THE NEW ARCHITECTURAL LAYAOUT. NEW SPRINKLER HEADS ADDEED AS REQUIRED.
THE MECHANICAL WORK INCLUDES INSTALLATION OF NEW DUCTWORK AND DIFFUSERS IN THE TENNAT SCAPE
INTERIOR RENOVATION OF AN EXISTING 556 SQ.FT SPACE AND IT INCLUDES RECONFIGURATION OF THE INTERIOR WALLS & DOOR AND INSTALLATION OF NEW EQUIPMENT AND FIXTURES AS DEFINED IN NYC BUILDING CODE
8823 - Modification of interior storefront for Prada Beauty space. No change in egress, use, or occupancy.
8823 - Modification of Ductwork, Lighting and non bearing partitions in L'Oreal space. No change in egress, use, or occupancy.
Installation of sidewalk shed for public protection during construction work, no change on egress
Installation of pipe scaffold for access to areas of work, no change on egress or occupancy, ACP5 Control Number: 11076401
8823 - Modification of Ductwork, Lighting and non bearing partitions in L'Oreal space. No change in egress, use, or occupancy.
Modification related to sprinkler systems on cellar (lower level) as indicated on attached plans. There is no change in egress, use or occupancy.
Modification to the existing Plumbing and Sprinkler system on the ground FL la Prairie Store. No change of use, egress and occupancy.
MINOR RENOVATION OF EXISTING COMMERCIAL SPACE ON THE GROUND FLOOR. ARCHITECTURAL WORK TYPE. NO CHANGE TO USE, OCCUPANCY, OR EGRESS.
General construction of LA Prairie retail space on the 1st FL in Bloomingdales. No change of use, egress or occupancy.
4TH FLOOR DUCT WORK, INSTALLATION OF MOTORIZED DAMPER AND REMOTE BUTTON SENSOR, RELOCATION OF TEMPERATURE CONTROLS AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY
Temporary structures for a Bloomingdale's event. Structures to be removed at the end of the programing. No changes to existing structures, use or egress.
SPRINKLER HEADS INSTALLATION AND RELOCATION AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Modification to the existing Plumbing and Sprinkler system on the ground FL la Prairie Store. No change of use, egress and occupancy.