1294 1 AVENUE, Manhattan, NY, 10021 · New York City · 36 total events
SUPPORT OF EXCAVATION FOR THE CONSTRUCTION OF A NEW BUILDING AS PER PLANS FILED HEREWITH.
FOUNDATION WORK FOR THE CONSTRUCTION OF A NEW BUILDING AS PER PLANS FILED HEREWITH.
INSTALLATION OF CONSTRUCTION FENCE FOR NEW BUILDING CONSTRUCTION AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. CONSTRUCTION FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE.
TEMPORARY ROOF PROTECTION AT ADJOINING PROPERTIES DURING BLDG ALTERATION, FILED SEP. TEMPORARY ROOF PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY SHORING AS PER DRAWINGS. SHORING SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY CRASH DECK PLATFORM AS PER DRAWINGS. CRASH DECK PLATFORM SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
HEAVY DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
CONSTRUCTION FENCE AS PER DRAWINGS. CONSTRUCTION FENCE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Curtain Wall Glass Demolition
full demolition of 16 story structure using hand held and mechanical means to assist.
solid perimeter protection for mechanical demolition of concrete slab.
Mechanical means will be used in accordance with approved demolition plans.
Engineered enclosure protection will be built as per BC
Demo of rooftop mechanical units and support dunnage and water tank.
SINGLE #7000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING BLDG ALT FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY
Protections and Mechanical methods for hoist demo floors 1 thru 9
Partial slab demolition to create openings for future temporary hoist floors 1 thru 9
installation of chutes to lower demolition debris from floor to floor
INSTALLATION OF AN AIR PRESSURIZED STANDPIPE SYSTEM DURING ENTIRE BUILDING DEMOLITION AS PER PLANS SUBMITTED HEREWITH, NO CHANGE IN USE, EGRESS OR OCCUPANCY GROUP.
Interior demolition of non load bearing elements
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Non Structural Demolition, Interior Renovations filed herewith. No Change in Use, Egress or Occupancy
INSTALL NON-ILLUMINATED WALL SIGN (GIVENCHY)
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
new sprinkler drain line from cellar to 18th floor
ERECT NON-ILLUMINATED CABINET ON EXISTING CANOPY ON MADISON AVE ELEVATION. ERECT NON-ILLUM BLADE SIGN ON E.59TH STREET ELEVATION. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Relocate3 sprinkler heads and add 1 new.
AC unit replacement as per plans.
Verizon - Installation of telecommunication antenna sectors, GPS units and step over on the roof. Installation of new cabinets in the equipment room on the 18th floor. All work is in compliance with TPPN 5/98. No change in use, egress or occupancy.
Filing for removal of fire hose as per plans herewith Penthouse (1)18th Floor (1) Cellar through 17th floor (3 each). No change in use, egress or occupancy under this application.
Erect non-illuminated accessory business wall sign readingSantoni
REPLACEMENT OF 5 TON CAPACITY UNIT ON THE 2ND FLOOR KITCHEN. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
Relocate duct work and piping.
INSTALLATION OF PIPE SCAFFOLD AS SHOWN ON DRAWINGS. NO CHANGE IN USE EGRESS OR OCCUPANCY. WE SHALL COMPLY WITH CHAPTER 33 OF 2014 B.C
Modification of Existing Antenna site. Installation of an additional telecom cabinet on existing equipment platform. Install (3) additional antennas with related filters & RRUs on the roof. All work is in conformance with TPPN #5/98. No change in use, exits or occupancy. Carrier: Sprint