117 NINTH AVENUE, Manhattan, NY, 10011 · New York City · 16 total events
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INTERIOR RENOVATION TO COMBINE EXISTING UNITS 6B AND 6C INTO 6BC AS PER TPPN #3/97. PLEASE NOTE, THIS BUILDING IS NOT IN THE WCH SPECIAL DISTRICT.
PLUMBING WORK FOR THE INTERIOR RENOVATION TO COMBINE EXISTING UNITS 6B AND 6C INTO 6BC AS PER TPPN #3/97. PLEASE NOTE, THIS BUILDING IS NOT IN THE WCH SPECIAL DISTRICT.
PLUMBING WORK FOR THE INTERIOR RENOVATION TO COMBINE EXISTING UNITS 23G AND 23H INTO 23GH AS PER TPPN #3/97. PLEASE NOTE, THIS BUILDING IS NOT IN THE WCH SPECIAL DISTRICT.
INTERIOR RENOVATION TO COMBINE EXISTING UNITS 23G AND 23H INTO 23GH AS PER TPPN #3/97. PLEASE NOTE, THIS BUILDING IS NOT IN THE WCH SPECIAL DISTRICT.
Applying for temporary sidewalk shed on behalf of building owner
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AS PER THE PLANS. NO CHANGE IN USE, EGRESS AND OCCUPANCY
THE SCOPE OF WORK PROVIDING NEW ROOF OPENING FOR DUCT IN EXISTING ROOF SLAB,INCREASING EXISTING WALL OPENING FOR DUCT.
This project is to make current Kitchen Hoods Exhaust System(serving the electric Range Exhaust Hood and a hood for electric oven), provide one exhaust fan to serve both hoods and provide a makeup air unit to replace exhausted air.
This application if filed for temporary use permit for hospital occupancy pursuant to section AC 28-111 in conjunction with covid 10 vaccinations.
Removal of (3) branch gas lines: Two (2) 3/4 gas line in the commercial kitchen. One (1) 3/4 gas line in the training room kitchen. Removal of one (1) gas shut-off valve on 3/4 gas supply to range in the commercial kitchen.
FN/ 119 9th Avenue SUBMITTING ON BEHALF OF CONTRACTOR FOR THE INSTALLATION OF TEMPORARY CONSTRUCTION EQUIPMENT FENCE on grade to protect public from roof WORK AT BUILDING .NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Judgment: NO
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CHAIN LINK FENCE AS PER PLANS. CHAIN LINK FENCE SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.