111 WASHINGTON STREET, Manhattan, NY, 10006 · New York City · 22 total events
Use of mini crane as per plans filed herewith.
INSTALLATION OF COCOON SYSTEM IN CONJUNCTION WITH NB 121192299. THIS APPLICATION INVOLVES NO CHANGE IN USE, OCCUPANCY OR EGRESS.
INSTALLATION AND USE OF TEMPORARY STANDING STAIR TOWER AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Installation and use of contractor shed as per plans filed herewith. This application is filed in conjunction with New Building BIS 121192299
Filing temporary standpipe in conjunction with NB job# 121192299
Installation of sprinkler/standpipe system associated with NB Construction. NB filed under 121192299. Project filed under 2014 building code but such is not selectable in DOBNOW. Job grandfathered into 2014 Code as per BB 2022-007.
Installation of sprinkler/standpipe system associated with NB Construction. NB filed under 121192299. Project filed under 2014 building code but such is not selectable in DOBNOW. Job grandfathered into 2014 Code as per BB 2022-007.
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Application filed for underground plumbing in conjunction with NB Construction. NB filed under 121192299.
INSTALLATION OF TEMPORARY OVERHEAD PROTECTION PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE OVERHEAD PROTECTION AT 110 GREENWICH ST ROOFS/TERRACE. AND IN THE COURTYARD EAST AT 102 &110 & 108 & 106 GREENWICH STREET BUILDINGS.
INSTALLATION OF TEMPORARY CHIMNEY PROTECTION PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE 4 CHIMNEYS RPTOECTION ON 109 WASHINGTON ST AND 1 CHIMNEY PROTECTION ON 110 GREENWICH ST.
INSTALLATION OF TEMPORARY ROOF PROTECTION PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE ROOF PROTECTION AT NEIGHBOR ROOF AT 109 WASHINGTON STREET AND 110 GREENWICH STREET.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN. THERE IS NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE SIDEWALK SHED AT WASHINGTON STREET AND CARLISLE STREET ELEVATIONS..
INSTALL OF TEMPORARY WINDOW PROTECTION PER PLAN. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. THE WINDOW PROTECTION ON 4 WINDOWS ON THE S ELEV AT 110 GREENWICH ST AND W ELEV 108 GREENWICH ST, 14 WINDOWS ON THE SW CORNER AT 110 GREENWICH ST AND ON THE CORNER
NORTH HOISTS-CARS 1&2: EQUIPMENT USE: DUAL 7400# CAPACITY PERSONNEL/MATERIAL HOISTS DURING NB FILED SEP. HOISTS SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEP.
SOUTH HOIST - CAR 3: EQUIPMENT USE: SINGLE #7000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEP
INSTALLATION OF TEMPORARY FENCE AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY BARRICADE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY PLYWOOD FENCE AS PER PLAN. NO CHANGE IN USE,EGRESS OR OCCUPANCY.
Temporary foundations associated with temporary steel framing to offset reinforced masonry building at the adjacent tax lot. Filed in conjunction with NB# 121192299.
Application filed for pile installation only. Pile Caps designed and installed under related NB# 121192299.
Temporary foundations associated with temporary steel framing to offset reinforced masonry building at the adjacent tax lot. Filed in conjunction with NB# 121192299.