Remove & replace existing concrete floor deck with new concrete floor on the metal deck. Remove existing steel framing with new steel framing. Work to be performed at Con Edison's 59th Street Generating Station at 2nd Floor.
Remove & replace existing concrete floor deck with new concrete floor on the metal deck. Remove existing steel framing with new steel framing. Work to be performed at Con Edison's 59th Street Generating Station at 2nd Floor.
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Facade Repairs at Con Edison's 59th Street Gen Station. Landmark approval to perform work has been received, CNE-23-02145. (Cycle 9A)
Con Edison's 59th Street Station - SWARMP (GC work type) Facade Repairs. ......PAA - The asbestos documentation originally required for this application (V5) has changed, (An ACP-5 will be generated instead) Reason will appear in comments section
HVAC modifications: remove exhaust fans from the 59th street annex battery room, install new supply & exhaust fans, install new supply air duct work, install new heaters, remove and install new louvers, provide new floor penetrations for the new supply ai
Make general repairs to roof R10 and R11 at Con Edison's 59th Street Generating Station.
Filing sidewalk shed as per plans filed.
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.