NYU - Skirball Lab Modernization - SPRINKLER, STANDPIPE MODERNIZATION ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - SPRINKLER, STANDPIPE MODERNIZATION ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Herewith filing plumbing modifications for NYU Lipton Hall 18th Floor Apartment. No change in use, egress, or occupancy.
HEREWITH FILING FOR GENERAL CONSTRUCTION MODIFICATIONS FOR LIPTON HALL RENOVATION (APARTMENT 18A). NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
Herewith filing plumbing modifications for NYU Lipton Hall 19D, 23D, 23F, 23J, and 23L Apartments. No change in use, egress, or occupancy.
HEREWITH FILING FOR GENERAL CONSTRUCTION MODIFICATIONS FOR LIPTON HALL RENOVATION (APARTMENTS 19F, 19D, 23A, 23B, 23K, 23D, 23F, 23J, 23L). NO CHANGES TO USE, EGRESS, OR OCCUPANCY.
NYU - Skirball Lab Modernization Fit Out - MODIFICATION OF PARTITIONS, CEILING, DOORS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - STRUCTURAL MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - MECHANICAL MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - INTERIOR DEMOLITION MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - STRUCTURAL MODIFICATIONS FOR DEMOLITION ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - MECHANICAL MODIFICATIONS FOR DEMOLITION ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYU - Skirball Lab Modernization - SPRINKLER DEMOLITION MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2014.
Herewith filing Sprinkler Standpipe modifications for NYULH Outpatient Lab. No change in use, egress, or occupancy.
Herewith filing Sprinkler Standpipe modifications for NYULH Outpatient Lab. No change in use, egress, or occupancy.
NYU - Skirball Lab Modernization - PLUMBING MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
INSTALLATION OF TEMPORARY PERSONNEL/MATERIAL HOIST AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. CONSTUCTION HOIST TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODEOF 2014.
INSTALLATION OF TEMPORARY LOBBY PLATFORM SCAFFOLD AS PER PLANS DURING GENERAL CONSTRUCTION WORK. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SCAFFOLD TO COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2014.
Herewith filing Sprinkler modifications for Skirball 10th floor N/Q Renovations. No change in use, egress, or occupancy.
Herewith filing plumbing modifications for NYULH Outpatient Lab. No change in use, egress, or occupancy.
Herewith filing general construction modifications for NYULH Outpatient lab. No change in use, egress, or occupancy.
Herewith filing mechanical modifications for NYULH Outpatient Lab. No change in use, egress, or occupancy.
Herewith filing general construction modifications for Lipton Hall Renovation (21st Floor). No change in use, egress, or occupancy.
Herewith filing general construction modifications for Lipton Hall Renovation (20th Floor). No change in use, egress, or occupancy.
Herewith filing plumbing modifications for Lipton Hall Renovation (21st Floor). No change in use, egress, or occupancy.
Herewith filing plumbing modifications for Lipton Hall Renovation (20th Floor). No change in use, egress, or occupancy.
Herewith filing plumbing modifications for Lipton Hall Renovation (14th Floor). No change in use, egress, or occupancy.
Herewith filing plumbing modifications for Lipton Hall Renovation (11th Floor). No change in use, egress, or occupancy.
Herewith filing general construction modifications for Lipton Hall Renovation (11th Floor). No change in use, egress, or occupancy.
Herewith filing general construction modifications for Lipton Hall Renovation (14th Floor). No change in use, egress, or occupancy.
Herewith filing General Construction modifications for Skirball 10th Floor Suite N/Q and Suite W Renovations. No change in use, egress, or occupancy.
Includes system of cooling only water source heat pumps serving interior spaces. Ventilation provided by connection to existing system. Toilet exhaust ducts reconfigured to align with new architectural requirements on 10th floor Skirball.
NYU - Skirball Lab Modernization - PLUMBING DEMOLITION MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
The scope of this project is to fit out a portion of the cellar level with a new sprinkler layout. No change in use, egress, or occupancy
Scope of this project is to fit out a portion of the cellar level to serve new plumbing fixtures to accommodate the new architectural design
the scope of this project is to fit out a MRI suite and elec closet on the cellar floor to accommodate the new MRI equipment
herewith filing for a full renovation of existing MRI suite, associated MRI equipment storage space and electric closet in the cellar. No change in use, egress, or occupancy
ROOF REPLACEMENT. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
STRUCTURAL WORK IN CONJUNCTION WITH ROOF REPLACEMENT. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Herewith filing Plumbing modifications for Skirball 9th and 10th Floor N/Q Renovations. No change in use, egress, or occupancy.
herewith filing for general construction modifications as per plans. no change in use, egress or occupancy.
Herewith filing Plumbing modifications for Lipton Hall Renovation (23rd Floor). No change in use, egress, or occupancy.
Herewith filing General Construction modifications for Lipton Hall Renovation (17th Floor). No change to use, egress, or occupancy.
Herewith filing Plumbing modifications for Lipton Hall Renovation (22nd Floor). No change in use, egress, or occupancy.
Herewith filing Plumbing modifications for Lipton Hall Renovation (17th Floor). No change in use, egress, or occupancy.
HEREWITH FILING RENOVATION OF (3) LIPTON HALL BEDROOM APARTMENTS (APARTMENTS 22C, 22E, 22J). NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
REMOVAL OF EGRESS DOORS & HARDWARE AT 11TH FLOOR STAIR B AND C. INSTALLATION OF NEW SECURITY GATES INSTALLED ATFLOORS 3, 5, 7, 9, 13, 15, 17, & 21
NYU -Skirball - STRUCTURAL MODIFICATIONS FOR HIGH PRESSURE STEAM PIPE MODIFICATIONS ACCORDING TO PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.