MODIFICATION TO THE MECHANICAL SYSTEM. NO CHANGE IN USE, OCCUPANCY AND EGRESS.
REMOVAL AND INSTALLATION OF INTERIOR NON-LOAD BEARING PARTITIONS, DOORS, CEILING AND ASSOCIATED FINISHES ON THE 15TH [MARKETING] 14TH [CONSTRUCTION]. NO CHANGE IN USE, OCCUPANCY AND EGRESS.
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES, SPRINKLER HEADS AND ASSOCIATED PIPING ON THE 15TH [MARKETING] 14TH [CONSTRUCTION]. NO CHANGE IN USE, OCCUPANCY AND EGRESS
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES, SPRINKLER HEADS AND ASSOCIATED PIPING ON THE 15TH [MARKETING] 14TH [CONSTRUCTION]. NO CHANGE IN USE, OCCUPANCY AND EGRESS
New replacement slab with temp shorting
Filing to modify Plumbing fixtures and Sprinkler system as well as Pre-action sprinkler system at floors 29-31 (Marketing floors 30-32) as per plans. No change in use, egress, or occuapncy under this application.
Filing interior renovation at existing accessory 4th floor space with partition, door, floor, and finish work as per plans. No change in use, egress, or occupancy under this application.
Filing to repair concrete slab in Penthouse Elevator machine room as per plans. No change in use, egress, or occupancy under this application.
Mechanical work at 2nd floor for existing MCU space.
MODIFICATION TO THE MECHANICAL SYSTEM. NO CHANGE IN USE, OCCUPANCY AND EGRESS.
REMOVAL AND INSTALLATION OF INTERIOR NON-LOAD BEARING PARTITIONS, DOORS, CEILING AND ASSOCIATED FINISHES ON THE 14TH [MARKETING] 13TH [CONSTRUCTION]. NO CHANGE IN USE, OCCUPANCY AND EGRESS.
INFILL OF EXISTING STAIR OPENING. NO CHANGE IN USE, OCCUPANCY AND EGRESS.
CREATE A NEW OPENING IN THE CONCRETE SLAB TO ACCOMMODATE A NEW STAIR. INSTAL NEW FOLDING PARTITION SUPPORT HANGERS. NO CHANGE IN USE, OCCUPANCY AND EGRESS.
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES, SPRINKLER HEADS AND ASSOCIATED PIPING ON THE 14TH [MARKETING] 13TH [CONSTRUCTION]. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
REMOVAL AND INSTALLATION OF PLUMBING FIXTURES, SPRINKLER HEADS AND ASSOCIATED PIPING ON THE 14TH [MARKETING] 13TH [CONSTRUCTION]. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
Interior renovation at 2nd floor for existing MCU space.
Sprinkler Work at 2nd floor for existing MCU Space.
Plumbing work at 2nd floor for existing MCU space.
Filing to modify Plumbing fixtures and Sprinkler system as well as Pre-action sprinkler system at floors 29-31 (Marketing floors 30-32) as per plans. No change in use, egress, or occuapncy under this application.
Structural reinforcing at 29th and 30th floors. Extension of stair from 29th to 30th floors.
Filing to modify HVAC and Ventilation systems at construction floor 29-31 as per plans. No change in use, egress, or occupancy under this application.
Filing interior renovation of existing offices with Partitions, ceilings, doors, and finishes as per plans. No change in use, egress, or occupancy under this application.
Filing to modify plumbing, sprinkler, and standpipe systems at 7th and 25th (26th marketing floors as per plans. No change in use, egress, or occupancy under this application.
Dish:Installation of new telecommunication antenna sectors, GPS antenna&equipment cabinet on a new platform on roof. Installation of conduits & service room connection as per plans.All work is in compliance with 5/98. No change in use, egress or occupancy
Filing to modify plumbing, sprinkler, and standpipe systems at 7th and 25th (26th marketing floors as per plans. No change in use, egress, or occupancy under this application.
Filing to provide Structural support/reinforcement as needed at 7th and 25th construction floors as per plans. No change in use, egress, or occupancy under this application.
Filing to modify plumbing, sprinkler, and standpipe systems at 7th and 25th (26th marketing floors as per plans. No change in use, egress, or occupancy under this application.
Filing to modify existing HVAC system at 7th and 25th (26 marketing) floors as per plans. No change in use, egress, or occupancy under this application.
Filing interior renovation of existing commercial spaces at 7th and 25th construction floors as per plans submitted. No change in use, egress, or occupancy under this application.
MODIFICATION OF SPRINKLERS ON 29TH FLOORS (DOE) AS PER PLANS FILED HEREWITH.
Interior architectural modifications as per shown on plans filed herewith. Filed in conjunction with mechanical application B00648359-I1 and sprinkler application B00648399-I1. No change in egress, occupancy or use.
Interior Mechanical Modifications as per shown on plans filed herewith. Filed in conjunction with General construction application B00647911-I1 and sprinkler application B00648399-I1. No change in egress, occupancy or use.
Sprinkler modifications as per shown on plans filed herewith. No change in egress, occupancy, or use.
INTERIOR DEMOLITION AND INSTALLATION OF PARTITIONS ON 28TH & 29TH FLOORS ASSOCIATED WITH RENOVATION OF OFFICE SPACES FOR THE (DOE). NO CHANGE IN USE EGRESS OR OCCUPANCY.
MODIFICATION OF DUCTWORK, RELOCATE DIFFUSERS AND GRILLES AND REBALANCE MECHANICAL SYSTEM.
PLUMBING MODIFICATIONS ON 28TH & 29TH FLOOR (DOE) AS PER PLANS FILED HEREWITH.
removal and installation of plumbing fixtures, sprinkler heads and associated piping on the 26th floor (LTK). no change in use, occupancy or egress.
removal and installation of plumbing fixtures, sprinkler heads and associated piping on the 26th floor (LTK). no change in use, occupancy or egress.
Removal and installation of interior non-load bearing partitions, doors, ceilings and associated finishes on the 26th floor (LTK). No change in use, occupancy or egress.
constant volume air distribution to hvac sheet metal ductwork and air outlets on the 26th floor (LTK). relocation and replacement of existing vav units and controls. no change in use, occupancy or egress.
MODIFICATIONS TO SPRINKLER SYSTEM ON 21ST, 22ND AND 23RD FLOOR (NYCERS) AS INDICATED ON DRAWINGS.
Modification to existing Verizon telecommunications site. Replace 9 antennas, remove 3 antennas, and install 3 new RRH units and 3 new antennas on roof. All in conformance with TPPN 5/98. No change in use, egress, or occupancy
PROPOSING TO EXTEND EXISTING BUILDING HVAC SYSTEM TO SERVICE RENOVATED OFFICE SPACES AT 21ST, 22ND AND 23RD FLOORS AS INDICATED ON DRAWINGS. ADDING NEW DUCTWORK, VAV BOXES AND DIFFUSERS.