465 37 STREET, Brooklyn, NY, 11232 · New York City · 13 total events
INSTALLATION OF NEW GAS PIPING TO NEW GAS BOOSTER TO SUPPLY NEW KILN EQUIPMENT IN THE 3RD FLOOR
mechanical modifications for HVAC installation to the 5th floor as per plans filed herewith. No change in use, egress or occupancy.
APPLICATION FILED HEREWITH FOR FACADE RESTORATION WORK AS SHOWNON PLANS SUBMITTED. NO CHANGE IN USE,EGRESS OR OCCUPANCY UNDER THISAPPLICATION
Plumbing modifications as per shown on plans filed herewith. Filed in conjunction with BE application M00787484-I1. No change in egress, occupancy, or use.
Installation of low pressure hot water condensing boilers as shown on plans filed herewith. Filed in conjunction with plumbing application M00781839-I1. No change in egress, occupancy or use.
SUPPORTED SCAFFOLD FOR WORKER ACCESS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
STORAGE ON SIDEWALK SHED. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
SIDEWALK SHED FOR PROTECTION OF PUBLIC. NO CHANGE IN USE, EGRESS, OR OCCUPANCY
Mechanical modifications as per shown on plans filed herewith. Filed in conjunction with general construction application M00719011-I1 and Structural application M00719418-I1. No change in egress occupancy, or use.
Architectural interior modifications as per shown on plans filed herewith. Filed in conjunction with mechanical systems application M00719087-I1 and Structural application M00719418-I1. No change in egress, occupancy or use.
Structural Modifications as shown on plans filed herewith. Filed in conjunction with general construction application M00719011-I1 and Mechanical application M00719087-I1. No change in egress, occupancy, or use.
TEMPORARY INSTALLATION AND USE OF SUPPORTED SCAFFOLD AS PER PLANS FILED HERE WITHIN. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
REMOVE AND REPLACE 3 EXISTING GAS RISERS WITH 1 NEW RISER AND PIPING TO SUPPORT EXISTING GAS EQUIPMENT. WORK IS BEING PERFORMED TO CORRECT LL 152/2016 DEFICIENCIES NOTED WITHIN GAS PIPING SYSTEM PERIODIC INSPECTION REPORT DATED 3/5/2021.