26 3 PLACE, Brooklyn, NY, 11231 · New York City · 16 total events
Provide One BX Spilt cooling system of size and capacity scheduled to service the MDF room, including wiring, thermostats, piping, insulation and all associated appurtenances.
PROPOSED INSERTS, HANGERS, TRENCHES, PITS, CONDUITS IN WALLS AND SLABS EQUIPMENT SUPPORT, ELEVATOR DIVIDER BEAMS, EMBEDMENTS, AND ANCHOR RODS IN ELEVATOR SHAFT.
INSTALLATION OF CONSTRUCTION FENCE AT 18 BEAVER STREET - BROOKLYN, AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF PIPE SCAFFOLD AT 18 BEAVER STREET - BROOKLYN, AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 18 BEAVER STREET - BROOKLYN, AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
K120-NEW LIGHTING : Installation of 12 Units of Exterior Perimeter Lighting at the cellar area and 7 Units of Exterior Perimeter Wall Lighting on the 1st floor area
K120 : EXT MASONRY, PARAPETS & ROOF WORK including Roof Curb Re-flashing and Roof to Roof Re-flashing, replacement of Coping Stones, Extension of the Parapet Walls with Steel Tube Fences to meet Minimum Height Requirements for the Parapet walls.
PROVIDE NEW EXHAUST FANS AND TO ACCOMMODATE NEW AND UPGRADED TOILETS, INSTALL NEW OR MODIFY EXISTING DUCT WORK AS SHOWN ON DRAWINGS. PROVIDE SPLIT HEAT PUMP FOR NEW ELEVATOR MACHINE ROOM. PROVIDING LIGHTING AS SHOWN ON PLANS.
Support of Excavation at the interior of the basement for new Elevator pit.
NEW PLUMBING FIXTURES AND ASSOCIATED PIPING. NEW HOT WATER DISTRIBUTION FROM HEAT PUMP HOT WATER HEATER TO SERVE 1ST AND 2ND FLOOR PLUMBING FIXTURES.
PROPOSED INSERTS, HANGERS, TRENCHES, PITS, CONDUITS IN WALLS AND SLABS EQUIPMENT SUPPORT, ELEVATOR DIVIDER BEAMS, EMBEDMENTS, AND ANCHOR RODS IN ELEVATOR SHAFT.
PROPOSED INSERTS, HANGERS, TRENCHES, PITS, CONDUITS IN WALLS AND SLABS EQUIPMENT SUPPORT, ELEVATOR DIVIDER BEAMS, EMBEDMENTS, AND ANCHOR RODS IN ELEVATOR SHAFT.
REMOVAL AND REPLACEMENT OF MASONRY, PARTITIONS, DOORS AND HARDWARE; INTERIOR FINISHES. REPLACEMENT OF ELEVATOR WITH NEW.
K120 : MECHANICAL WORK : Gravity ventilators, Exhaust fans, Duct works
K120 : PLUMBING WORK : Replace 16 Roof Drains; 28 Vent Stacks Extensions and relocate 2 Vent Stacks on the Roofs. Remove 1 Gas Range, 1 2-Compartment Sink, 1 Dishwasher, 2 Drainage, 1 Grease Interceptor, 1 Ansul System, 2 Sprinkler heads, Gas Shut-Off
APARTMENT ONLY