INSTALLATION OF NEW SIDEWALK SHED FOR PS 75X AT 984 FAILE STREET, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF PIPE SCAFFOLD FOR PS 75X AT 984 FAILE STREET, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF DEBRIS CHUTE FOR PS 75X AT 984 FAILE STREET, BRONX AS PER INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION SHORING FOR EXCAVATION FOR PS 75X AT 984 FAILE STREET, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE FOR PS 75X AT 984 FAILE STREET, BRONX AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Improvements to the existing building ventilation system including general construction work necessary to modify ductwork.
Removal of asphalt, tables/benches, and fence. New asphalt, play structures, safety surface, fence and gates, tree grates, privacy slats, benches, tables, planters, and painted markings.
Installation of 200 ft of Temporary Construction Fence , at the building , No change of Use or Egress Or Occupancy of the building.
SH/PS 75X - FOR TEMPORARY CONSTRUCTION EQUIPMENT(Emergency SHED) SUBMITTING ON BEHALF OF CONTRACTOR, IN CONJUNCTION WITH LLW# 115853 NO CHANGE IN USE, OCCUPANCY OR EGRESS