INSTALLING NEW MECHANICAL EQUIPMENT, INCLUDING BUT NOT LIMITED TO PUMPS, HEAT EXCHANGERS, CONTROL VALVES, EXPANSION TANK, AND HOT WATER SYSTEM BTU METER AT WALSH HALL. NOCHANGE OF USE, EGRESS OR OCCUPANCY.
INSTALLATION OF NEW DOMESTIC HOT WATER HEATER INCLUDING NEW DOMESTICWATER PIPING AND INSTALLATION OF NEW NATURAL GAS PIPING. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
INSTALLING NEW MECHANICAL EQUIPMENT, INCLUDING BUT NOT LIMITED TO CONTROL VALVES AND A HOT WATER SYSTEM BTU METER AT JOHN MULCAHY HALL. NO CHANGEOF USE, EGRESS OR OCCUPANCY
INSTALLATION OF NEW DOMESTIC HOT WATER HEATER INCLUDING NEW DOMESTICWATER PIPING. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Civil work that includes flood mitigation for the existing parking, as shown on the drainage and stormwater plans. No change of use, egress or occupancy.
Keating Hall, Roof repair PHASE 2- removal and replacement of the roofing membranes/components above the existing roof deck down to the existing concrete deck and installation of a new perimeter guardrail. No change of use, egress and occupancy.
INSTALLATION OF TEMPORARY BETA MAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
FILING HEREWITH THE ISNTALLATION OF TWO (2) BLOOM ENERGY ES5 OUTDOOR NATURAL GAS CLEAN ENERGY SERVERS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS PROPOSED UNDER THIS APPLICATION.
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Repairs and conservation of university church. Including masonry replacement, replication, and repair of deteriorated architectural features; repairs to exterior to provide watertight envelope per plans. No change in use, egress or occupancy.
Structural scope associated with the Bepler Chair Laboratory on 001FL renovation at Freeman Hall. No change of use, egress or occupancy.
Architectural scope associated with the Bepler Chair Laboratory on 001FL renovation at Freeman Hall and minor work on the 2-3 floors. No change of use, egress, or occupancy.
Mechanical scope associated with the Bepler Chair Laboratory on 001FL renovation at Freeman Hall. No change of use, egress, or occupancy.
Like kind replacement of roof top packaged system. There is no change in use, occupancy, or egress.
mechanical work associated with legal council offices renovation as shown on the drawings filed herewith, no change to use, egress or occupancy
interior and exterior renovation for the legal council offices as shown on the drawings filed herewith, no change to use, egress or occupancy
INSTALLATION AND USE OF TEMPORARY SUPPORTED SCAFFOLD AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
INSTALLATION OF TEMPORARY SHANTY AS PER DWGS. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
structural repairs of existing slab at St John's as shown on plans filed herewith. No change to use, egress or occupancy
Temporary tents on lawns for Fordham Univ. Programming. Removed after use. TPAs required for 75 persons or more. No changes to existing structures, use or egress Weather plan required
removal and replacement of chiller and associated piping on part of cellar
TEMPORARY INSTALLATION AND USE OF SIDEWALK SHED AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Mechanical work associated with the proposed renovation of the existing football locker room as shown on the plans filed herewith. No change to use, egress, or occupancy.
Plumbing work associated with the proposed renovation of the existing football locker room as shown on the plans filed herewith. No change to use, egress, or occupancy.
the proposed renovation of the existing football locker room as shown on the plans filed herewith. No change to use, egress or occupancy.
Structural work associated with the proposed renovation of the existing football locker room as shown on the plans filed herewith. No change to use, egress, or occupancy.
Partial demolition of chimney as per plans filed herewith.
INSTALLATION OF TEMPORARY BETA MAX HOIST AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Mechanical work associated with the installation of a new combustion air fan at the Thebaud Hall. No change of use, egress, or occupancy.
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
John Mulcany Hall - Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
MECHANICAL SCOPE ASSOCIATED WITH THE OFFICE RENOVATION AT O'HARE HALL. NO CHANGE OF USE, EGRESS OR OCCUPANCY.
Structural scope associated with the interior renovation of the existing offices at O'Hare Hall. No change of use, egress, or occupancy.
Architectural scope associated with the interior renovation of the existing offices at O'Hare Hall. No change of use, egress, or occupancy.
FILING HEREWITH FOR REMOVAL OF TEMPORARY EGRESS STAIR AND INSTALLATION OF NEW CURTAIN WALL WINDOW AS PER PLANS.
FACADE INSPECTION
Plumbing and Sprinkler scope associated with the offices renovation at O'Hare Hall. No change of use, egress or occupancy.
Plumbing and Sprinkler scope associated with the offices renovation at O'Hare Hall. No change of use, egress or occupancy.
Decommissioning of one (1) existing 15,000-gallon underground fuel oil (No.4 Fuel Oil) tank to be abandoned in place and filled with FDNY-approved foam, removal of all associated piping. No change of use, egress or occupancy.
structural work associated with south wings roof repair as shown on plans filed herewith. no change to use, egress, or occupancy.
Plumbing scope associated with the Bepler Chair Laboratory on 001FL renovation at Freeman Hall. No change of use, egress, or occupancy.
Keating Hall- removal and replacement of the roofing membranes/components above the existing roof deck down to the existing concrete deck and installation of a new perimeter guardrail. No change of use, egress and occupancy.
Plumbing work associated with LAB 530 renovation. No change to use, egress or occupancy.
INSTALLATION OF TEMPORARY WORK PLATFORM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. WORK PLATFORM SHALL COMPLY WITH CHAPTER 33 OF NYC BUILDING CODE OF 2022.
Mechanical work associated with LAB 530 renovation. No change to use, egress or occupancy.
STRUCTURAL SCOPE ASSOCIATED WITH RENOVATION OF JMH LAB 530 AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE OF USE, EGRESS, OR OCCUPANCY.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AND PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.LIVE LOAD 300PSF.
RENOVATION OF JMH LAB 530 AS SHOWN ON PLANS FILED HEREWITH. NO CHANGE OF USE, EGRESS, OR OCCUPANCY.
FILING HEREWITH THE INSTALLATION OF FOUR (4) BLOOM ENERGY ES5 OUTDOOR NATURAL GAS CLEAN ENERGY SERVERS AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY IS PROPOSED IN THIS APPLICATION.