169 17 STREET, Brooklyn, NY, 11215 · New York City · 14 total events
INSTALLATION OF TEMPORARY SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY OVERHEAD PROTECTION AS PER DRAWINGS DURING BLDG ALTERATION FILED SEP. OVERHEAD PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
KC Criminal Courthouse, FISP related exterior facade repairs as per the plans filed: Cooper roofing repairs/ replacing & reattaching. Stone repairs pinning, resetting, crack, spall, mortar joint & spall. Door/window joint sealant repairs. Reattach antenna
Remove 1 20k gallon fuel oil UST and associated piping and eq and install 1 19,194k gallon fuel oil UST, 1 1,500 gallon diesel UST and associated piping, eq and leak detection with associated GE, earth work, structural steels reinforcement, and concrete
Install one new 1,500 gallon ultra low sulfur diesel UST and all associated equipment. Restore all areas disturbed by construction as shown on drawings filed herewith. No change in use egress or occupancy under this application
INSTALLATION OF CONSTRUCTION FENCE AS PER PLANS. CONSTRUCTION FENCE SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE PER PLAN SUBMITTED. WORK SHALL COMPLY WITH 2014 BUILDING CODES CHAPTER 33. NO CHANGE IN USE, EGRESS AND/OR OCCUPANCY WITH THIS APPLICATION.
INSTALL TEMPORARY PREFABRICATED STEEL SUPPORT OF EXCAVATION SYSTEM TO FACILITATE THE NEW UNDERGROUND FUEL STORAGE TANK INSTALLATION ON SITE. NO CHANGE TO USE, EGRESS OR OCCUPANCY
Empty, Purge, Clean, Remove & Dispose of one out-of-service 20,000-Gallon #2 fuel oil UST, and all associated equipment. Install one new 19,194-Gallon double-wall steel #2 fuel oil UST, and all associated equipment, Restore all areas (see comments)
Installation of a temporary heavy-duty sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of dry sprinkler heads in the interim sally port area and connection to the existing courthouse wet sprinkler system. No change in use, egress, or occupancy under this application.
Structural and General Construction for Interim Sally Port as shown on drawings filed herewith. No change in use, egress, or occupancy under this application.
Structural and General Construction for Interim Sally Port as shown on drawings filed herewith. No change in use, egress, or occupancy under this application.