Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE FILED IN CONJUNCTION WITH NB.
COMBINED SPRINKLER & STANDPIPE FILED IN CONJUNCTION WITH NB # B00678425-I1
Structural filed in conjunction with NB B00678425-I1
INSTALLATION AND USE OF TEMPORARY MOBILE MINI CRANE AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
COMBINED SPRINKLER & STANDPIPE FILED IN CONJUNCTION WITH NB # B00678425-I1
Installation of temporary air pressurized standpipe system during construction per LL 64/09, IN CONJUNCTION WITH GC # B00678425-I1
PLUMBING FILED IN CONJUNCTION WITH NB # B00678425-I1
Mechanical Application filed in conjunction with New Building B00678425-I1.
PROPOSED 11 STORY MIXED USE BUILDING TOTAL OF 92 DWELLING UNITS.
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of temporary needle beam per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of 7,000# temporary dual cars personnel/material hoists in conjunction with NB# B00678425-I1 per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Cellar plumbing filed in conjunction with NB GC # B00678425-I1
Foundation filed subsequent to NB GC # B00678425-I1
SOE IN CONJUNCTION WITH NB