128 3 PLACE, Brooklyn, NY, 11231 · New York City · 42 total events
Roofing hoist installation
Relocation of existing DAIKIN ACCU unit. Extension of all vent pipes, new insulation on all refrigerant piping, cleaning & restoration of smoke vents, cleaning & painting of post indicator valves. Retrofit roof drains, irrigation system heads & controls.
NYCT Namm Hall facade repairs & complex plaza upgrade: Repair, Removal & Replacement of existing plaza roof membrane, railing, expansion joint, install new canopy, brick masonry & brick repointing, parapet, window and sealant replacement.
Sidewalk Shed Installation
REPLACEMENT OF EXISTING ROOF DRAINS, PIPING, BULKHEAD STORM GUTTER & PIPING WITH NEW AT SAME LOCATIONS ON ROF AS PER PLANS
INSTALLATION OF SIDEWALK SHED FOR EXTERIOR WORK AT BUILDING FACADES
REPLACEMENT OF EX. MAIN ROOFING SYSTEM, MEMBRANE FLASHING, MAIN ROF PARAPET + BULKHEAD FOR LIBRARY BLDG (L) OF NYCCT. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Modification to existing AT&T site. Install 2 new antennas, replace 2 existing antennas, retrofit 1 existing equipment cabinets.
INSTALL NON-ILLUMINATED WALL SIGN (CITY TECH)
MECHANICAL WORK AS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
SF/Cuny City Tech - FOR TEMPORARY CONSTRUCTION EQUIPMENT( (Scaffold)SUBMITTING ON BEHALF OF CONTRACTOR. NO CHANGE IN USE,OCCUPANCY OR EGRESS
REMOVE EX. CTRL VALVE(S) & CHILLED WATER SUPPLY PIPING. FURNISH AND INSTALL NEW PRESSURE INDEPENDENT CONTROL VALVE, ISOLATION VALVE(S) & NEW CHILLED WATER SUPPLY CONNECTIONS TO EX. MH SYSTEM IN CEL,BAS,1-7,9,PEN. NO CHANGE IN USE, EGRESS OR OCCUPANCY
INTERIOR RENOVATION OF AN EXISTING OFFICES, INCLUDING PARTITION CHANGES. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
SPRINKLER WORK AS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 300 JAY STREET, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 300 JAY STREET, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Installation of a temporary heavy-duty sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
PLUMBING WORK AS PER PLANS. NO CHANGE OF USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
§27-2107 ADM CODE OWNER FAILED TO FILE A VALID REGISTRATION STATEMENT WITH THE DEPARTMENT AS REQUIRED BY ADM CODE §27-2097 AND IS THEREFORE SUBJECT TO CIVIL PENALTIES, PROHIBITED FROM CERTIFYING VIOLATIONS, AND DENIED THE RIGHT TO RECOVER POSSESSION OF PREMISES FOR NONPAYMENT OF RENT UNTIL A VALID REGISTRATION STATEMENT IS FILED.
REMOVE EX. CTRL VALVE(S) & CHILLED WATER SUPPLY PIPING. FURNISH AND INSTALL NEW PRESSURE INDEPENDENT CONTROL VALVE, ISOLATION VALVE(S) & NEW CHILLED WATER SUPPLY CONNECTIONS TO EX. MH SYSTEM ON 5TH FL. NO CHANGE IN USE, EGRESS OR OCCUPANCY
INSTALLATION OF PIPE SCAFFOLD AT 300 JAY STREET, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
INSTALLATION OF NEW SIDEWALK SHED AT 300 JAY STREET, BROOKLYN AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
NYCT Namm Hall Exterior faade repairs as per the plans filed including: Removal/Repairs/Replacement of spalled concrete, stone panel, brick masonry and sealant joint. Localized cracked window glazing replacement. Stone & brick masonry joint repointing.
FILING MODIFICATION TO EXISTING HVAC SYSTEM AND INSTALLATION OF NON REFRIGERANT UNIT AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
INSTALLATION OF SIDEWALK SHED AS PER PLANS. SIDEWALK SHED LIVE LOAD WILL BE 300 PSF, ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE NO CHANGE TO USE, EGRESS OR OCCUPANCY.
NYC Tech. Namm Hall, ATS Elevator Room Design at cellar, as per the plans filed including: Installation of fire rated room with non-load bearing CMU walls. Removal/replacement/relocation of doors. Enclosure of masonry opening.
sprinkler modification
mechanical modification
minor interior demo, new partition, doors and finishes
structural work as per plans
INSTALLATION OF SIDEWALK SHED & CONSTRUCTION FENCE FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED & CONSTRUCTION FENCE SHALL COMPLY WITH NYCC 2014 CHAPTER 33 . NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
INSTALLATION OF SIDEWALK SHED & CONSTRUCTION FENCE FOR PEDESTRIAN SAFETY DURING CONSTRUCTION. SIDEWALK SHED & CONSTRUCTION FENCE SHALL COMPLY WITH NYCC 2014 CHAPTER 33 . NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
NAMM HALL COOLING TOWER - STEEL DUNNAGE REPAIR AT MAIN ROOF AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY PLACEMENT OF A JEKKO SPX424 MINI CRAWLER CRANE (CONSTRUCTION EQUIPMENT) TO HOIST AND INSTALL GLASS PANELS
MODIFICATIONS TO EXISTING SPRINKLER SYSTEM
INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Furnish and install temporary loop on the 2nd floor.
Replacement of existing telephone room A/C units & associated piping. There is no change in use, egress or occupancy.
INSTALLATION OF PIPE SCAFFOLD IN ACCORDANCE WITH NYCC 2014 CHAPTER 33. NO CHANGE IN EGRESS, USE, OR OCCUPANCY.
EXISTING T-MOBILE ANTENNA SITE. REPLACEMENT OF (8) EXISTING ANTENNAS ON EXISTING MOUNTS AND INSTALLATION OF (9) NEW ANTENNAS AND (15) RRU'S. ALL IN CONFORMANCE WITH TPPN 5/98. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
AT&T / Replacement of existing telecommunications antennas with replacement/installations of RRH units on roof. Removal and installation of cabinets in the existing equipment platform on roof, All work in compliance with TPPN 5/98. No change to occupancy, use or egress.