1 10 STREET, Brooklyn, NY, 11215 · New York City · 16 total events
HEREWITH FILING FOR INTERIOR REMOVAL OF NON LOAD BEARING PARTIONS
2500# CAPACITY MATERIAL ONLY HOIST AS PER DRAWINGS DURING BLDG ALTERATION, FILED SEPARATELY. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
TEMPORARY HOIST RUN-BACK STRUCTURE DURING BUILDING ALTERATION, FILED SEPARATELY. RUN-BACK STRUCTURE SHALL COMPLY WITH CH #33 OF THE NYC BLDG CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
HEAVY DUTY SIDEWALK SHED DURING BLDG ALTERATION, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
CONSTRUCTION FENCE AS PER DRAWINGS. CONSTRUCTION FENCE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. DOT PERMITS BY OTHERS FOR FENCE INSTALLED ON SIDEWALK/ROADWAY.
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. PIPE SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Modification to existing SP system related to alteration including connection of new SP main/branch, new SP control valve assembly & connection to base system. Repair & extension of existing SD system to level 4 to supply new floor control valve assembly
Modification to existing SP system related to alteration including connection of new SP main/branch, new SP control valve assembly & connection to base system. Repair & extension of existing SD system to level 4 to supply new floor control valve assembly
MODIFICATION TO PLUMBING FIXTURES AND ASSOCIATED PIPING RELATED TO ALTERATION.
New eating and drinking establishment to first floor. Modify seating layout in theater with no increase in total occupant count of theater.
HEREWITH FILING FOR INTERIOR REMOVAL OF HVAC, PIPING AND DUCT WORK
Mechanical work including demolition and installation of new equipment, ductwork and louvers related to alteration.
Installation of steel framing for new openings, trenching at cellar, new catwalk, new dunnage at roof level. Installation of new steel framing for repair of existing dunnage at roof level & re-framing of tech loft at 4fl level.
HEREWITH FILING FOR REMOVAL OF EXTERIOR HVAC
HEREWITH FILING FOR INTERIOR REMOVAL OF EXISTING PLUMBING FIXTURES TO BE REMOVED AND REPLACED WITH NEW PLUMBING FIXTURES. ALLEXISTING ASSOCIATED PIPING TO BE CUT, CAPPED, AND PREPPED FOR RE-CONNNECTION TO NEWREPLACED PLUMBING FIXTURES
INSTALL OF TEMP PLATFORM, NO ALTERATIONS TO EXIST STRUCTURES, FOR THE EVENT SIRIUS XM PRESENTS U2 AT THE APOLLO THEATER. Temporary structures will be removed after the event.