FACADE RESTORATION TO COMPLY WITH FISP AS PER DRAWINGS SUBMITTED HEREWITH. NO CHANGE IN USE, OCCUPANCY OR EGRESS,
BATHTUB/SHOWER
CABINET
PESTS
MOLD
PESTS
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. LIVE LOAD 300PSF.
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
Installation of suspended scaffold for facade inspection/repair.
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
SCOPE OF WORK IS TO PROVIDE NEW DOMESTIC WATER, VENT AND SANITARY PIPING TO ALL NEW FIXTURES WITHIN THE SPACE. BASE BUILDING VENT, SANITARY AND DOMESTIC COLD WATER WILL BE UTILIZED TO FOR THE SPACE. DOMESTIC HOT WATER WILL BE PRODUCED FOR THE NEW FIXTURES
SCOPE OF WORK IS TO PROVIDE NEW DOMESTIC WATER, VENT AND SANITARY PIPING TO ALL NEW FIXTURES WITHIN THE SPACE. BASE BUILDING VENT, SANITARY AND DOMESTIC COLD WATER WILL BE UTILIZED TO FOR THE SPACE. DOMESTIC HOT WATER WILL BE PRODUCED FOR THE NEW FIXTURES
New concrete pad and steel platform to support new generator.
Proposed interior alteration at first floor, including installation of two (2-hour) rated partitions for proposed switchboard room, and installation of generator at exterior yard.
MECHANICAL SCOPE IN CONJUNCTION WITH MEDICAL OFFICE RENOVATION AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
INTERIOR RENOVATION TO AND EXISTING VACANT 'B' SPACE AND ADJACENT OCCUPIED 'B' SPACE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Installation of suspended scaffold for facade inspection/repair.
PESTS
PESTS
HEAVY FLOW
CEILING
INST CONCRETE PAD FOR ROOF TOP UNIT (RTU-1) ON 5TH FL ROOF, INST STL DUNNAGE BEAMS FOR EXH FANS (EF-1 AND EF-2) CONNECTING TO EX BEAMS ON THE ROOF LEVEL, INSTALL STL BRACKETS TO SUPPORT STAINLESS STL DUCT AND LINTELS FOR DUCT PENETRATION ON EXTERIOR WALL
Proposed Installation of outdoor 5 Ton package unit including supply and return duck work, diffusers, returns grills, toilet exhaust complete. To serve New Pharmacy Clean Room.
PROPOSED: INSTALLATION OF NEW WATER TREATMENT SYSTEM AND NEW PIPING ROUTED TO SERVE HUMIDIFIER, INSTALLATION OF NEW SINK AND DRAINAGE PUMP FOR THE CLEAN ROOM AND ANOTHER SINK FOR THE ADJACENT PHARMACY.
Installation of 23 sprinkler heads including sprinkler piping.
INSTALLATION OF 300psf SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
INSTALLATION OF 300psf SIDEWALK SHED AND PIPE SCAFFOLDING AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER # 33 OF THE 2014 CODE. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
Propose to install sign. No change in use, egress, or occupancy.
Replacement of HVAC Unit and associated ducts and piping on 3rd floor, minor duct alterations, expansion of Verizon Wireless Cage as shown on drawings filed herewith. No change in use, egress or occupancy.
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED 425 LENGTH x 8 - 14 HEIGHT WITH DOUBLE LEGS AND RATED 300 PSF AND 600 PSF FOR MATERIAL STORAGE AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
install sign on wall. no change in use, egress or occupancy
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING BUILDING ALTERATION, FILED SEPARATELY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.