TUCKPOINTING AND UNIT MASONRY REPAIR / REPLACEMENT: 25 SQ. FT., LINTEL QTY. 0, MAX. LENGTH 0. LOCATION: ALL EXTERIOR FACADE ELEVATIONS.
TUCKPOINTING AND UNIT MASONRY REPAIR / REPLACEMENT: 25 SQ. FT., LINTEL QTY. 0, MAX. LENGTH 0. LOCATION: ALL EXTERIOR FACADE ELEVATIONS.
LEAKING BOILER TUBES
OWNER OR LICENSED CONTRACTOR
REPLACE
STAY-BOLTS
ERECT ONE (1) SCAFFOLD DATES 08/16/2023 THROUGH 08/16/2024
GRIND & TUCKPOINT WHERE NECESSARY AT LIMSTONE AND MASONRY(APPROX 200 SQ FT),REMOVE/REPLACE DETERIORATED MASONRY(20 SQ FT),ROUT & SEAL LIMESTONE CRACKS.
MAINTAIN OR REPAIR ELECT ELEVA
WINDOWS (REPLACEMENT ONLY): QTY 15
UNIT 4N: REMOVE/REPLACE KITCHEN CABINETS, REFNISH FLOORS, REPLACE PLUMBING FIXTURES AND PIPING IN 3 BATHROOMS AND KITCHEN, REPLACE PLASTER WITH DRYWALL, NO FLOOR PLAN ALTERATIONS, SEPARATE ELECTRICAL PERMIT REQ'D
- ADD 3 NEW ELECTRICAL CIRCUITS - R&R ALL ELECTRICAL OUTLETS AND SWITCHES - R&R APPROX 20 CEILING AND WALL LIGHT FIXTURES - ADD OUTLET IN LR AND PER CODE IN KITCHEN
SELF-CERT 2019 CBRC: REVISION TO PERMIT 100958469 TO REPLACE 6 FIRE RATED WINDOWS AND ONE EXIT DOOR TO THE FIRE ESCAPE ONLY AT CONDO UNIT 9N AS PER PLAN. NO INTERIOR RENO. WORK. (OCCUPANY GROUP R-2, TYPE IA CONSTRUCTION)
LAUNDRY CLOSET UNIT#26 ONLY:OPEN CLOSET WALL FOR PLUMBING WORK. REPAIR AND REPLACE EXISTING PLUMBING D,W.V AND WATER CONNECTIONS FOR WASHER. SUPPLY AND INSTALL NEW GRAY BOX PLUMBING AND CONNECT WATER SUPPLY LINES. REPAIR DAMAGES AFTER WORK UP TO THE PRIMER. EXISTING ELECTRICAL TO REMAIN IN PLACE.
SELF-CERT 2019 CBRC: INTERIOR ALTERATION TO A DUPLEX UNIT IN A MULTI-FAMILY HIGHRISE AS PER PLANS. NO ADDITIONAL AREA CREATED, NO EXTERIOR WORK. RECONFIGUREATION OF UNIT SPACES PER PLAN. (OCCUPANY GROUP R-2, TYPE IA CONSTRUCTION)
11-S: MASTER BATHROOM REMODEL, REPAIR AND REPLACE PLUMBING FIXTURES AND ASSOCIATED PIPING IN UNIT 11-S
UNIT #5-N ONLY: WEST BATHROOM REMODEL:REMOVE/REPLACE - TUB/SHOWER, SINK, FAUCET, CABINET, MIRROR, FLOOR TILES, CROWN MOLDING, CEMENT BOARD TO BOTTOM OF SHOWER WALL, CUSTOM BUILD A SHAMPOO NIECHE NO EXTERIOR WORK.
TUCKPOINTING - NO STRUCTURAL WORK - 2350 SQFT. MASONRY REPAIRS
ERECT TWO(2)SCAFFOLDS FROM 03/23/2021 TO 03/23/2022.
UNIT 6C ONLY - WINDOWS (REPLACEMENT ONLY): QTY 10
WINDOWS (REPLACEMENT ONLY): QTY 3 AT 26TH FLR PER ARCH. DRAWING
SELF-CERT: INTERIOR DEMOLITION AND WOOD WINDOW RESTORATION IN EXISTING DUPLEX DWELLING UNIT ON THE 9TH AND 10TH FLOORS OF A MULTI-FAMILY HIGH RISE BUILDING. MEP WORK PER PLANS. NO CHANGE IN OCCUPANCY.
ADD CIRCUITS FOR BEDROOM AND BATHROOM IN UNIT 14S
¿ALL ELEVATIONS, REPAIR/REPLACE BRICK 1000 SQ. FT., TUCK-POINT 2000 SQ. FT., REPAIR/REPLACE SEALANT 2000 LINEAR FT., REPAIR/REPLACE MASONRY CRACKS 2000 LINEAR FT., REPAIR/REPLACE 50 STONE DUTCHMAN, REPAIR/REPLACE 100 BRICK ANCHORS, REPAIR/REPLACE 2000 LINEAR FT. FLASHING AT STEEL SHELF ANGLE/STEEL BEAM REMEDIATION, REPAIR/REPLACE/CLEAN SHELF ANGLES/STEEL BEAM REMEDIATION, ONLY¿
No details available
ERECT SCAFFOLD FROM 03/15/2019 TO 03/15/2020.
HOLDOPEN DEVICE ON APT DOOR
2-HR STAIR ENCLOSURE, 4+ STORY
DEBRIS, EXCESSIVE
SELF-CLOSE CLASS B FIRE DOOR
SELF-CLOSE DOOR >4 STORY RES.
OBSTRUCTIONS IN EXIT WAY
MAINTAIN EXIT SIGN ILLUMINATED
ILLUMINATE PUBLIC STAIR/HALL
INSTALL SMOKE DETECTORS
REPAIR EXTERIOR DOOR
PIPE OPENING W/NONCOMBUST MATL
PROTECT METAL MEMBERS
SEND EX. METAL LETTER
REPAIR EXTERIOR WALL
REMOVE
REMOVE
SEND EX. METAL LETTER