CBRC 2019: INSTALLATION OF THREE NEW (3) COOLING TOWERS TO THE ROOF AND NEW CHILLER ON THE FIRST FLOOR OF AN EXISTING WEST CAMPUS COMBINED UTILITY PLANT AS PER PLANS (CONSTRUCTION TYPE 1A / OCCUPANCY F-2)
SPR 2019 CBRC: WEST CAMPUS COMBINED UTILITY PLAN (OCCUPANCY F-2). RENOVATE EXISTING OFFICE ARE INTO NEW WOMENS LOCKER ROOM WITH BATHROOM AND ONE OFFICE. MODIFY EXISTING MEP/FP SYSTEMS TO ACCOMMODATE NEW ROOM USE.
SPR 2019 CBRC: WEST CAMPUS COMBINED UTILITY PLAN (OCCUPANCY F-2). RENOVATE EXISTING OFFICE ARE INTO NEW WOMENS LOCKER ROOM WITH BATHROOM AND ONE OFFICE. MODIFY EXISTING MEP/FP SYSTEMS TO ACCOMMODATE NEW ROOM USE.
REPLACEMENT OF HOIST CABLES ON ONE(1) 1000LB CAPACITY, 200FPM, 6-FLOOR, TRACTION, PASSENGER ELEVATOR, PURSUANT TO THE SCOPE OF WORK SUBMITTED.(W. CHILLER COMB UTILITY PLANT)