407 N Elizabeth St, Chicago, IL, 60642 · Chicago · 17 total events
TUCKPOINTING AND UNIT MASONRY REPAIR / REPLACEMENT: 100 SQ. FT., LINTEL QTY. 0, MAX. LENGTH 0. PARAPET REBUILDING: 50 SQ. FT. LOCATION: REAR AREA OF THE BUILDING 3RD FLOOR OUTSIDE 304.
REBUILD PARAPET WALL, REPLACE LINTELS UNDER 6', REMOVE/REPLACE COPING STONES WITH PROPER FLASHING
SPR 2019 CBRC - INTERIOR RENOVATION TO UNIT 103, TO RELOCATE WATER HEATER, REMOVE FIRPLACE, STAIR RAILING ALTERATIONS AND ELECTRICAL WORK AS PER PLANS - EXISTING BLDG IS 3 STORY/19 RESIDENTAL UNITS, TYPE IV
SELF CERT- REPLACE EXISTING ROOF TOP DECK SMALLER SIZE, SIMILAR LOCATION PER PLANS, CURRENT USE A-2, PROPOSED USE A-2
REPLACE (1) UNIT # 105A
REPAIR PARAPET WALL
PLUMBING ONLY,REPLACE WATER HEATER IN BASEMENT OF UNIT # 103
REPLACE 1 FURNACE
UNIT 103; REPLACING PLUMBING FIXTURES WITH ASSOCIATED PIPING IN TWO BATHROOMS AND KITCHEN,NEW SHOWER FAUCET 1ST AND 2ND FL,BATH FAUCET 2 ND FL,SINK FAUCETS 1 ST,2ND,FL BATHS AND KITCHEN,REPLACE WATER HEATER IN BASEMENT. SUBJECT TO FIELD INSPECTION.
INSTALL A FRESH AIR INTAKE FOR FIREPACE AND RELOCATING DRYER VENTS WITH DRYER BOOSTER PER INSPECTOR KOPKA REQUEST.
ENCLOSING THREE WINDOWS IN HOISTWAY/SHAFT TO CORRECT EV1110 VIOLATION; BRICKING UP WITH 8" CMU AND BRICK
REPLACE 1 FURNACE
REPLACE THE EXISTING SPLIT SYSTEM WITH ONE BRYANT 3 1/2 TON SPLIT SYSTEM,AIR COOLED, R410A, LOCATED ON THE ROOF, SERVING UNIT #205.
MASONRY REPAIRS INCL PAPAPET WALL AND CRACKS; TUCKPOINTING - NO STRUCTURAL WORK - 2000 S QFT; REPLACE BRICKS
REPLACE AND REPAIR LIGHT FIXTURES, INSTALLED SMOKE AND CO DETECTORS, REPAIR EXIT AND EMERGENCY LIGHT SYSTEM, REPLACE EXISTING OUTLETS WITH GFCI OUTLETS.
BATHROOM REMODEL INCLUDING REPLACE TUB, SHOWER, VANITY/SINK AND TOILET.WORK TO BE DONE IN UNIT 302 ONLY. NO ELECTRICAL WORK ON PERMIT.
NORTH 2 STORY BUILDING SECTION ROOF REPAIRS/REPLACEMENT AND FLASHING WORK. NO STRUCTURAL WORK UNDER SCOPE. (APPROXIMATELY 10,000SQFT)